Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
23 Jul 2021 | Rail crossing work pending due to non getting permission from railway. | Koothuparamba Proj AE 2 | |
21 Jul 2021 | Rail crossing permission pending.All other works completed and commissioned on 08/02/2020 | Koothuparamba Proj AE 2 | |
19 Jul 2021 | Rail crossing permission is pending.Valuation certificate which was asked by Raiway is submitted.Report from GCE kannur is not obtained. | Koothuparamba Proj AE 2 | |
17 Jul 2021 | Rail crossing permission pending. | Koothuparamba Proj AE 2 | |
15 Jul 2021 | Rail crossing permission pending.Railway authorities again asked some more report .Requsted to GCE kannur for reports. | Koothuparamba Proj AE 2 | |
13 Jul 2021 | Rail crossing permission pending | Koothuparamba Proj AE 2 | |
12 Jul 2021 | Rail crossing permission pending.Valuation certificate from village office received.Report from GCE Kannur is pending | Koothuparamba Proj AE 2 | |
10 Jul 2021 | Rail crossing permission pending.Report regarding with the thrust force from GCE kannur is under preperation.Contacted the department several times.Expecting the report on next monday. Valuation certificate from village office will received by monday. | Koothuparamba Proj AE 2 | |
08 Jul 2021 | Rail crossing permission pending | Koothuparamba Proj AE 2 | |
06 Jul 2021 | Rail crossing pending | Koothuparamba Proj AE 2 |