| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 12 Apr 2025 | Pipe laid 2300 m out of 2300 m and FHTC 1127Nos out of 2150 Nos completed, first and final bill under preparation | Kannur WS Sn AE 2 | |
| 09 Apr 2025 | Pipe laid 2300 m out of 2300 m and FHTC 1127Nos out of 2150 Nos completed, first and final bill under preparation | Kannur WS Sn AE 2 | |
| 06 Apr 2025 | Pipe laid 2300 m out of 2300 m and FHTC 1127Nos out of 2150 Nos completed, first and final bill under preparation | Kannur WS Sn AE 2 | |
| 03 Apr 2025 | Pipe laid 2300 m out of 2300 m and FHTC 1127Nos out of 2150 Nos completed, first and final bill under preparation | Kannur WS Sn AE 2 | |
| 31 Mar 2025 | Pipe laid 2300 m out of 2300 m and FHTC 1127Nos out of 2150 Nos completed, first and final bill under preparation | Kannur WS Sn AE 2 | |
| 28 Mar 2025 | Pipe laid 2300 m out of 2300 m and FHTC 1127Nos out of 2150 Nos completed, first and final bill under preparation | Kannur WS Sn AE 2 | |
| 24 Mar 2025 | Pipe laid 2300 m out of 2300 m and FHTC 1127Nos out of 2150 Nos completed, first and final bill under preparation | Kannur WS Sn AE 2 | |
| 22 Mar 2025 | Pipe laid 2300 m out of 2300 m and FHTC 1127Nos out of 2150 Nos completed, first and final bill under preparation | Kannur WS Sn AE 2 | |
| 18 Mar 2025 | Pipe laid 2300 m out of 2300 m and FHTC 1127Nos out of 2150 Nos completed, first and final bill under preparation | Kannur WS Sn AE 2 | |
| 15 Mar 2025 | Pipe laid 2300 m out of 2300 m and FHTC 1127Nos out of 2150 Nos completed, first and final bill under preparation | Kannur WS Sn AE 2 |