Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
02 Dec 2024 | Pipe laid 2000 m out of 2300 m and FHTC 1050 Nos out of 2150 Nos completed,, Road restoration work in progress | Kannur WS Sn AE 2 | |
29 Nov 2024 | Pipe laid 2000 m out of 2300 m and FHTC 1050 Nos out of 2150 Nos completed,, Road restoration work in progress | Kannur WS Sn AE 2 | |
26 Nov 2024 | Pipe laid 2000 m out of 2300 m and FHTC 980 Nos out of 2150 Nos completed,, Road restoration work in progress | Kannur WS Sn AE 2 | |
23 Nov 2024 | Pipe laid 2000 m out of 2300 m and FHTC 980 Nos out of 2150 Nos completed,, Road restoration work in progress | Kannur WS Sn AE 2 | |
21 Nov 2024 | Pipe laid 2000 m out of 2300 m and FHTC 980 Nos out of 2150 Nos completed,, Road restoration work in progress | Kannur WS Sn AE 2 | |
18 Nov 2024 | Pipe laid 2000 m out of 2300 m and FHTC 980 Nos out of 2150 Nos completed,, Road restoration work in progress | Kannur WS Sn AE 2 | |
15 Nov 2024 | Pipe laid 2000 m out of 2300 m and FHTC 980 Nos out of 2150 Nos completed,, Road restoration work in progress | Kannur WS Sn AE 2 | |
12 Nov 2024 | Pipe laid 2000 m out of 2300 m and FHTC 980 Nos out of 2150 Nos completed,, Road restoration work in progress. | Kannur WS Sn AE 2 | |
09 Nov 2024 | Pipe laid 2000 m out of 2300 m and FHTC 980 Nos out of 2150 Nos completed,, Road restoration work in progress. | Kannur WS Sn AE 2 | |
06 Nov 2024 | Pipe laid 2000 m out of 2300 m and FHTC 980 Nos out of 2150 Nos completed,, Road restoration work in progress. | Kannur WS Sn AE 2 |