Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
21 Apr 2025 | 132834 m pipe laid 340 HTC and 891 FHTC | Koothuparamba Proj AE 2 | |
15 Apr 2025 | 132834 m pipe laid 343 HTC and 851 FHTC | Koothuparamba Proj AE 2 | |
11 Apr 2025 | 132834 m pipe laid 362 HTC and 732 FHTC | Koothuparamba Proj AE 2 | |
08 Apr 2025 | 132834 m pipe laid 379 HTC and 712 FHTC | Koothuparamba Proj AE 2 | |
05 Apr 2025 | 132834 m pipe laid 379 HTC and 712 FHTC | Koothuparamba Proj AE 2 | |
03 Apr 2025 | 132834 m pipe laid 407 HTC and 682 FHTC | Koothuparamba Proj AE 2 | |
29 Mar 2025 | 132834 m pipe laid 431 HTC and 647 FHTC | Koothuparamba Proj AE 2 | |
25 Mar 2025 | 132834 m pipe laid 443 HTC and 593 FHTC | Koothuparamba Proj AE 2 | |
19 Mar 2025 | 132834 m pipe laid 453 HTC and 568 FHTC | Koothuparamba Proj AE 2 | |