KIIFB -Kuttanad Drinking Water Project Phase II in Alappuzha District
Project |
KIIFB -Kuttanad Drinking Water Project Phase II in Alappuzha District |
Project Code |
ALPKIIFB0619635 |
Type |
Main project |
Funding Agency |
KIIFB |
Category |
KIIFB |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
Project covers the 13 panchayaths in Kuttanad Thaluk with source from Pampa river,30MLD water treatment plant at Neerettupuram, OHSR at 13 panchayths,Transmission lines and distribution network. |
Status |
On-going |
District |
Alappuzha |
Executing Office |
KIIFB Projects (ALP) |
AS Amount (Rs) |
2895400000
|
AS Number |
WRD 025-29/APR-6/2019/KIIFB |
TS Amount (Rs) |
|
TS Number |
|
Total Bill Submitted (Rs) |
223500000 |
Total Bill Paid (Rs) |
223500000 |
Population Benefitted |
212783 |
Capacity in MLD |
30.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
13 panchayaths in Kuttanad Thaluk |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
KIIFB -Kuttanad Drinking Water Project Package VII- Construction of OHSR and distribution network at Ramankary, Champakulam, with online chlorine booster at Ramankary OH tank site and rehabilitation of existing OHSR at Ramankary |
KIIFB Projects(ALP) |
|
2 |
KIIFB -Kuttanad Drinking Water Project Package - VIII- Construction of OHSR and distribution network at Nedumudy & Kainakary with online chlorine booster at Kainakary OH tank site and rehabilitation of existing OHSR at Nedumudi & Kainakary. |
KIIFB Projects(ALP) |
|
3 |
KIIFB -Kuttanad Drinking Water Project Phase II in Alappuzha District, Package-I |
KIIFB Projects(ALP) |
|
4 |
KIIFB -Kuttanad Drinking Water Project Phase II in Alappuzha District - Package-II |
KIIFB Projects(ALP) |
|
5 |
KIIFB -Kuttanad Drinking Water Project Phase II in Alappuzha District, Package-III |
KIIFB Projects(ALP) |
|
6 |
KIIFB -Kuttanad Drinking Water Project Phase II in Alappuzha District, Package-IV |
KIIFB Projects(ALP) |
|
7 |
KIIFB -Kuttanad Drinking Water Project Phase II in Alappuzha District, Package-V |
KIIFB Projects(ALP) |
|
8 |
KIIFB -Kuttanad Drinking Water Project Phase II in Alappuzha District, Package-VI |
KIIFB Projects(ALP) |
|
9 |
KIIFB -Kuttanad Drinking Water Project Phase II in Alappuzha District- Urgent laying of transmission and distribution lines along Alappuzha - Changanasserry road in connection with construction of semi Elevated Highway |
KIIFB Projects(ALP) |
|
10 |
KIIFB-Kuttanad WSS-Package 9-Construction of 4.75Lakhs Liters OHSR at Veeyapuram & Construction of Staff Quarters and office building at Edathua |
KIIFB Projects(ALP) |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
25 May 2023 |
Construction of 30MLD WTP and allied work tendered and single offer received. Package 4,5 work tendered and no offer received, Package 2 work tendered with due date 8/06/2023 . DPR for additional financial sanction for Rs. 98.37 crores was submitted on 03-10-2022. The file is under consideration by KIIFB. The wetland conversion process is pending at the LSGD directorate for Veeyapuram Panchayath. An amount of Rs. 21.80 crores was deposited to KSTP for the laying of the pipeline along AC road and work is about to start by KSTP through M/s ULCCS. On 18-3-2023 MD inspected the land acquired for the construction of proposed 30 MLD Water treatment plant and proposed intake structure and source at Nerettupuram. The drawings were verified.MD KWA explained the details and time lines regarding KIIFB Kuttanad WSS and the Action Plan on Jal Jeevan Mission works in the 13 Panchayaths of Kuttanad WSS Project. Honb’le MLA also pointed out the bottle necks in the pipe laying works along AC Road as part of KSTP Work and visited AC Road site. |
Kottayam Project Dn AEE2 KIFFB |
|
11 Apr 2023 |
Package 1 – Construction of 30MLD WTP and allied works tendered on 14-03-2023 with due date 17-04-2023, Package 4,5 TS issued and Package 2 submitted for TS . DPR for additional financial sanction for Rs. 98.37 crores was submitted on 03-10-2022. The file is under consideration by KIIFB. The wetland conversion process is pending at the LSGD directorate for Veeyapuram Panchayath. An amount of Rs. 21.80 crores was deposited to KSTP for the laying of the pipeline along AC road and work is about to start by KSTP through M/s ULCCS. On 18-3-2023 MD inspected the land acquired for the construction of proposed 30 MLD Water treatment plant and
proposed intake structure and source at Nerettupuram. The drawings were verified.MD KWA explained the details and time lines regarding KIIFB Kuttanad
WSS and the Action Plan on Jal Jeevan Mission works in the 13 Panchayaths of Kuttanad WSS Project. Honb’le MLA also pointed out the bottle necks in the pipe laying works along AC Road as part of KSTP Work and visited AC Road site. |
Alappuzha KIIFB - AE 1 |
|
18 Mar 2023 |
Package 1 – Construction of 30MLD WTP and allied works tendered on 14-03-2023 with due date 04-04-2023, Package 2,4,5 estimates submitted for TS.
DPR for additional financial sanction for Rs. 98.37 crores was submitted on 03-10-2022. The file is under consideration by KIIFB. The wetland conversion process is pending at the LSGD directorate for Veeyapuram Panchayath. An amount of Rs. 21.80 crores was deposited to KSTP for the laying of the pipeline along AC road and work is about to start by KSTP through M/s ULCCS. |
Alappuzha KIIFB - AEE 1 |
|
17 Mar 2023 |
Package 1 – Construction of 30MLD WTP and allied works tendered on 14-03-2023, Package 2,4,5 estimates submitted for TS . DPR for additional financial sanction for Rs. 98.37 crores was submitted on 03-10-2022. The file is under consideration of KIIFB. The wet land conversion process is pending at LSGD directorate for Veeyapuram Panchayath. An amount of Rs. 21.80 crores was deposited to KSTP for laying of pipe line along AC road and work is about to start by KSTP through M/s ULCCS. |
Alappuzha KIIFB - AE 1 |
|
24 Jan 2023 |
Estimates are ready for TS with designs. The meeting held on 01-08-2022 decided to arrange the tender as single package for the entire project. Based on the decision of meeting the DPR for additional financial sanction for Rs. 98.37 crores was submitted on 03-10-2022. The file is under consideration of KIIFB. The meeting held on 10-01-2023 at KIIFB office in presence of Hon'ble MLA Kuttanadu, it was decided to submit the estimate for TS for Package 1. The estimate will be submitted for TS with approved design from WASCON on 25-01-2023. The wet land conversion process is pending at LSGD directorate for Veeyapuram Panchayath and at Agriculture Production Commissioner office for Pulinkunnu Panchayath. An amount of Rs. 21.80 crores was deposited to KSTP for laying of pipe line along AC road and work is about to start by KSTP through M/s ULCCS |
Alappuzha KIIFB - AEE 1 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
25/06/2019 |
Scheduled date of Completion of the Project |
31 Dec 2022 |
Expected date of Completion |
31/12/2023 |