Project | KIIFB-Kuttanad WSS-Package 9-Construction of 4.75Lakhs Liters OHSR at Veeyapuram & Construction of Staff Quarters and office building at Edathua |
---|---|
Project Code | ALPKIIFB0619635P7 |
Type | Package |
Main Project | KIIFB -Kuttanad Drinking Water Project Phase II in Alappuzha District |
Funding Agency | KIIFB |
Category | KIIFB |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | KIIFB-Kuttanad WSS-Package 9-Construction of 4.75Lakhs Liters OHSR at Veeyapuram & Construction of Staff Quarters and office building at Edathua |
Status | On-going |
District | Alappuzha |
Executing Office | KIIFB Projects (ALP) |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 44400000 |
TS Number | WRD/KWA-CE(CR)/EST_TS/16426/2023 |
Technical specification |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | Date is not specified |
---|---|
Scheduled date of Completion as per agreement | Date is not specified |
Expected date of Completion | Date is not specified |
TS Date | 07 Dec 2023 |
---|---|
Estimate Approval | 07 Dec 2023 |
Alappuzha KIIFB - AE 1 |
Date: 06/05/2024 |
Work has started | 0% Completed
Work retendered, due date on 22/02/2024. No offer received, date extended up to 4/03/2024.No offer received, date extended up to 21/03/2024, No offer received, date extended up to 01/04/2024 , No offer received, date extended up to 15/04/2024. No offer received, date extended up to 02/05/2024. No offer received, date extended up to 24/05/2024..
Alappuzha KIIFB - AE 1 |
Date: 04/05/2024 |
Work has started | 0% Completed
Work retendered, due date on 22/02/2024. No offer received, date extended up to 4/03/2024.No offer received, date extended up to 21/03/2024, No offer received, date extended up to 01/04/2024 , No offer received, date extended up to 15/04/2024. No offer received, date extended up to 02/05/2024. No offer received, date extended up to 24/05/2024..