Project | KIIFB -Kuttanad Drinking Water Project Phase II in Alappuzha District, Package-V |
---|---|
Project Code | ALPGOK0619635P5 |
Type | Package |
Main Project | KIIFB -Kuttanad Drinking Water Project Phase II in Alappuzha District |
Funding Agency | KIIFB |
Category | KIIFB |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | Construction of OHSR and distribution network at Muttar , Veliyanadu, Neelamperoor with online chlorine booster at Neelamperoor OH tank site and rehabilitation of existing OHSR at Muttar, Veliyanad and Neelamperoor |
Status | On-going |
District | Alappuzha |
Executing Office | KIIFB Projects (ALP) |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | |
TS Number | |
Technical specification | OHSR and distribution network at Muttar (3.5 LL), Veliyanadu (4.5LL), Neelamperoor(5.5 LL) with online chlorine booster at Neelamperoor OH tank site and rehabilitation of existing OHSR at Muttar, Veliyanad and Neelamperoor |
Issue date | Solved On | Action Taken On | Category | Description | Comments | Issue Status |
---|---|---|---|---|---|---|
01 Oct 2021 | Pending | Pending | Road Cut Related Risk | Even though PWD informed the road restoration amount through portal, the detailed estimate not yet received. In some of the roads, the application is rejected stating that the ' road is under DLP' | No comments available. | Pending |
01 Sep 2021 | Pending | Pending | Road Cut Related Risk | The laying of pipeline in AC road has to be arranged along with the construction of AC road by KSTP. | No comments available. | Pending |
01 Sep 2021 | Pending | 23 Sep 2021 | Land Related Risk | 1) Land has to be acquired at Veliyanad for the construction of OHSR. Conversion of wet land is also required. | No comments added. | Action Taken |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | Date is not specified |
---|---|
Scheduled date of Completion as per agreement | Date is not specified |
Expected date of Completion | 31/12/2023 |
Alappuzha KIIFB - AE 1 |
Date: 06/05/2024 |
Work has started | 0% Completed
Work retendered, due date on 22/02/2024. No offer received, date extended up to 4/03/2024.No offer received, date extended up to 21/03/2024, No offer received, date extended up to 01/04/2024 , No offer received, date extended up to 15/04/2024. No offer received, date extended up to 02/05/2024. No offer received, date extended up to 24/05/2024..
Alappuzha KIIFB - AE 1 |
Date: 04/05/2024 |
Work has started | 0% Completed
Work retendered, due date on 22/02/2024. No offer received, date extended up to 4/03/2024.No offer received, date extended up to 21/03/2024, No offer received, date extended up to 01/04/2024 , No offer received, date extended up to 15/04/2024. No offer received, date extended up to 02/05/2024. No offer received, date extended up to 24/05/2024..