Project | KIIFB -Kuttanad Drinking Water Project Phase II in Alappuzha District- Urgent laying of transmission and distribution lines along Alappuzha - Changanasserry road in connection with construction of semi Elevated Highway |
---|---|
Project Code | ALPKIIFB0619635P10 |
Type | Package |
Main Project | KIIFB -Kuttanad Drinking Water Project Phase II in Alappuzha District |
Funding Agency | KIIFB |
Category | KIIFB |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | Urgent laying of transmission and distribution lines along Alappuzha - Changanasserry road in connection with construction of semi Elevated Highway |
Status | On-going |
District | Alappuzha |
Executing Office | KIIFB Projects (ALP) |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 21800000000 |
TS Number | TS/2021-2022/2021/42303 |
Technical specification |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | Date is not specified |
---|---|
Scheduled date of Completion as per agreement | 04 Sep 2024 |
Expected date of Completion | Date is not specified |
TS Date | 15 Feb 2022 |
---|
NA | 05 Sep 2023 |
---|
Alappuzha KIIFB - AE 4 |
Date: 06/05/2024 |
Work in progress | 3% Completed
Amount deposited to KSTP for executing work and work is progressing. HDPE pipe 50% supplied and remaining pipe's pipe test completed..
Alappuzha KIIFB - AE 4 |
Date: 04/05/2024 |
Work in progress | 3% Completed
Amount deposited to KSTP for executing work and work is progressing. HDPE pipe 50% supplied and remaining pipe's pipe test completed..