JJM-Functional Household Tap Connections, Distribution system, Construction of 60000 L capacity Service Reservoir cum BPT at Thannithadam and Laying 200mm DI K9 (1165 m ) Clear water Transmission main from Cheyodu GLSR to BPT Thannithadam at Vilakkudy Pt in Kollam

Project JJM-Functional Household Tap Connections, Distribution system, Construction of 60000 L capacity Service Reservoir cum BPT at Thannithadam and Laying 200mm DI K9 (1165 m ) Clear water Transmission main from Cheyodu GLSR to BPT Thannithadam at Vilakkudy Pt in Kollam
Project Code KLMJJM08203261
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Functional Household Tap Connections-8088 nos, Distribution system, Construction of 60000 L capacity Service Reservoir cum BPT at Thannithadam and Laying 200mm DI K9 (1165 m ) Clear water Transmission main from Cheyodu GLSR to BPT Thannithadam at Vilakkudy Pt in Kollam
Status On-going
District Kollam
Executing Office Kollam Project Dn
AS Amount (Rs) 290450000
AS Number GO(Rt)No:541/2020/WRD
TS Amount (Rs) 279400000
TS Number TS/2020-2021/2020/19334
Total Bill Submitted (Rs) 52769577
Total Bill Paid (Rs) 46055122
Population Benefitted 32995
Capacity in MLD 10.30
Actual Project Completion Date 07 Jan 2023
Coverage Vilakkudy Pt in Kollam
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 JJM-Functional Household Tap Connections, Distribution system, Construction of 60000 L capacity Service Reservoir cum BPT at Thannithadam and Laying 200mm DI K9 (1165 m ) Clear water Transmission main from Cheyodu GLSR to BPT Thannithadam at Vilakkudy Pt in Kollam Kollam Project Dn
2 JJM - Vilakkudi - Lastmile Conectivity Kollam Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
26 Feb 2024 Pipe laying work progressing. 76.057 Km laying completed. Construction of 60000 L capacity Service Reservoir cum BPT at Thannithadam - concrete works up to First brace beam completed- Reinforcement work of First brace beam in progress Kollam Project Dn AE
26 Jan 2024 Pipe laying work progressing. 76.057 Km laying completed. Construction of 60000 L capacity Service Reservoir cum BPT at Thannithadam - column concreting completed Kollam Project Dn AE
16 Jan 2024 Pipe laying work progressing. 76.057 Km laying completed. Construction of 60000 L capacity Service Reservoir cum BPT at Thannithadam - PCC completed Kollam Project Dn AE
26 Dec 2023 Pipe laying and Road restoration work in progress Kollam Project Dn EE
30 Nov 2023 Pipe laying work progressing Kollam Project Dn EE

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
14 Nov 2022 Pending Pending Road Cut Related Risk REVISED ROAD CUTTING PERMISSSION OF NH 744 No comments available. Pending

Duration & Sanction dates

Date of start of Project 08/01/2021
Scheduled date of Completion of the Project 07 Jan 2023
Expected date of Completion 31/12/2024

Processing Dates

AS Date 21 Aug 2020
TS Date 12 Sep 2020

Other details

Project Officers View