Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
26 Feb 2024 | Pipe laying work progressing. 76.057 Km laying completed. Construction of 60000 L capacity Service Reservoir cum BPT at Thannithadam - concrete works up to First brace beam completed- Reinforcement work of First brace beam in progress | Kollam Project Dn AE | |
26 Jan 2024 | Pipe laying work progressing. 76.057 Km laying completed. Construction of 60000 L capacity Service Reservoir cum BPT at Thannithadam - column concreting completed | Kollam Project Dn AE | |
16 Jan 2024 | Pipe laying work progressing. 76.057 Km laying completed. Construction of 60000 L capacity Service Reservoir cum BPT at Thannithadam - PCC completed | Kollam Project Dn AE | |
26 Dec 2023 | Pipe laying and Road restoration work in progress | Kollam Project Dn EE | |
30 Nov 2023 | Pipe laying work progressing | Kollam Project Dn EE | |
04 Nov 2023 | Pipe laying work progressing. Total geotagged - 2588 nos. | Kollam Project Dn AE | |
19 Oct 2023 | As per the proceedings no. KWA/PHC/Q/E1/5633/20223 dated 11.10.2023 of SE, PH Circle, kollam, list of works that has to be executed for the first 3 months on priority basis is issued to the contractor and work restarted on 18.10.2023 | Kollam Project Dn AE | |
04 Oct 2023 | Extended firm period ended on 07.07.2023. Further extension not granted. Detailed report & status of work submitted to agreement executed authority | Kollam Project Dn EE | |
05 Aug 2023 | Extended firm period ended on 07.07.2023. Further extension not granted. Detailed report & status of work submitted to agreement executed authority. | Kollam Project Dn AE | |
19 Jun 2023 | Pipe laying work progressing. Geotagged - 2582 nos | Kollam Project Dn EE |