Project | JJM - Vilakkudi - Lastmile Conectivity |
---|---|
Project Code | KLMJJM08203261P3 |
Type | Package |
Main Project | JJM-Functional Household Tap Connections, Distribution system, Construction of 60000 L capacity Service Reservoir cum BPT at Thannithadam and Laying 200mm DI K9 (1165 m ) Clear water Transmission main from Cheyodu GLSR to BPT Thannithadam at Vilakkudy Pt in Kollam |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM - Vilakkudi - Lastmile Conectivity and road restoration |
Status | On-going |
District | Kollam |
Executing Office | Kollam Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 19975000 |
TS Number | WRD/KWA-CE(SR)/EST_TS/13940/2023_26_1_1 |
Technical specification | Pipe line laying and road restoration work |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 05/04/2024 |
---|---|
Scheduled date of Completion as per agreement | 03 Mar 2025 |
Expected date of Completion | 31/12/2024 |
TS Date | 20 Nov 2023 |
---|---|
Estimate Approval | 13 Nov 2023 |
NIT Approval | 21 Nov 2023 |
Tender Closing | 04 Dec 2023 |
Technichal Pre-Qualification | 05 Dec 2023 |
Price bid opening | 05 Dec 2023 |
Workorder Date | 13 Feb 2024 |
---|---|
NA | 23 Feb 2024 |
Kollam Project Dn AE |
Date: 26/06/2024 |
Work in progress | 25% Completed
Pipeline work -5500m completed.
Kollam Project Dn AE |
Date: 25/06/2024 |
Work in progress | 25% Completed
Pipeline laying work in progress..