Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

JJM-Functional Household Tap Connections, Distribution system, Construction of 60000 L capacity Service Reservoir cum BPT at Thannithadam and Laying 200mm DI K9 (1165 m ) Clear water Transmission main from Cheyodu GLSR to BPT Thannithadam at Vilakkudy Pt in Kollam

Project JJM-Functional Household Tap Connections, Distribution system, Construction of 60000 L capacity Service Reservoir cum BPT at Thannithadam and Laying 200mm DI K9 (1165 m ) Clear water Transmission main from Cheyodu GLSR to BPT Thannithadam at Vilakkudy Pt in Kollam
Project Code KLMJJM08203261P1
Type Package
Main Project JJM-Functional Household Tap Connections, Distribution system, Construction of 60000 L capacity Service Reservoir cum BPT at Thannithadam and Laying 200mm DI K9 (1165 m ) Clear water Transmission main from Cheyodu GLSR to BPT Thannithadam at Vilakkudy Pt in Kollam
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Functional Household Tap Connections, Distribution system, Construction of 60000 L capacity Service Reservoir cum BPT at Thannithadam and Laying 200mm DI K9 (1165 m ) Clear water Transmission main from Cheyodu GLSR to BPT Thannithadam at Vilakkudy Pt in Kollam
Status On-going
District Kollam
Executing Office Kollam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 279400000
TS Number TS/2020-21/2020/19334
Technical specification FHTC-8088 Distribution system 60000L Service Reservoir cum BPT 200mm DI K9 Transmission main-1165m
Contractor J &B Engineering & construction company (Mob: 9447715266)

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
16 Apr 2021 Pending Pending Road Cut Related Risk Road crossing and Berm cutting Sanction pending in NH744 No comments available. Pending

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 08/01/2021
Scheduled date of Completion as per agreement 16 Dec 2022
Expected date of Completion 16/12/2022

Processing Dates

TS Date 12 Sep 2020
Estimate Approval 12 Sep 2020
NIT Approval 01 Oct 2020
Tender Closing 04 Nov 2020
Technichal Pre-Qualification 06 Nov 2020
Price bid opening 06 Nov 2020

Approval Dates

Workorder Date 17 Dec 2020
NA 08 Jan 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kollam Project Dn AE
Date: 26/06/2024

Work in progress | 49% Completed

Extended firm period exhausted. Detailed report & status of work submitted to agreement executed authority. Work stopped.

Kollam Project Dn AE
Date: 25/06/2024

Work in progress | 49% Completed

Firm period exhausted and notice issued to Contractor. Work stopped.