- Home
- KIIFB-WSS to Ala, Puliyoor, Budhanoor, P...
KIIFB-WSS to Ala, Puliyoor, Budhanoor, Pandanad, Mulakkuzha, Venmony Panchayaths and Chengannur Municipality-Package I
Project |
KIIFB-WSS to Ala, Puliyoor, Budhanoor, Pandanad, Mulakkuzha, Venmony Panchayaths and Chengannur Municipality-Package I |
Project Code |
ALPKIIFB0919495P1 |
Type |
Package |
Main Project |
KIIFB-WSS to Ala, Puliyoor, Budhanoor, Pandanad, Mulakkuzha, Venmony Panchayaths and Chengannur Municipality
|
Funding Agency |
KIIFB |
Category |
KIIFB WATER SUPPLY SCHEME |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
Construction of 35 MLD Water Treatment Plant with parallel plate clarifier, Renovation to existing Intake well cum Pump house -10 m Dia and Intake arrangements, Supply and laying Raw water Pumping main -700 DI K9 - 3050m Construction of OHSR 14.00 LL Capacity and 14.60 LL Sump cum Pump house at WTP, , Supply and erection testing and commissioning of raw water pump sets 270 HP VT 3 nos and Supply and erection testing commissioning of clear water pump set 75 HP CF-5 numbers, 25 HP CF-2 numbers, at clear water Sump, Substation and Transformer at intake pump house Kolamukkam, Design Supply, Erection, Testing and Commissioning of one No.750 KVA, 11 KV/3.30 K V Indoor Transformers and connected works at Raw Water Pump House, Kolamukkam, Substation and Transformer at WTP, Nikarumpuram Design, Supply, Erection, Testing and Commissioning of One Nos.400 KVA, 11 KV/433 V Indoor Transformers and connected works at WTP, Road Restoration works and allied works.
|
Status |
On-going |
District |
Alappuzha |
Executing Office |
KIIFB Projects (ALP) |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
388811875 |
TS Number |
TS/2019-2020/2020/569 |
Technical specification |
35 MLD Water Treatment Plant with parallel plate clarifier
Raw water Pumping main -700 DI K9 - 3050m
CWPM/CWGM - 400mm DI K9 pipe-380m, 350 mm DI K9 pipe-110m, 160 mm PVC 10 Kg pipe-1560m, 110 mm PVC 10 Kg pipe-2180m, 90 mm PVC 10 Kg pipe-740m, 75 mm PVC 10 Kg pipe-170m
Construction of OHSR 14.00 LL Capacity and 14.60 LL Sump cum Pump house at WTP
Raw water pump sets - 270 HP VT 3 nos
Clear water pump set - 75 HP CF-5 numbers, 25 HP CF-2 numbers. |
Contractor |
M/s Chicago constructions International pvt ltd (Mob: 9447770536) |
No project review have been added to this project
Reported Issues
Issue date |
Solved On |
Action Taken On |
Category |
Description |
Comments |
Issue Status |
30 Nov 2021 |
Pending |
Pending |
Road Cut Related Risk |
PWD permission not obtained |
No comments available. |
Pending |
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
19/10/2020 |
Scheduled date of Completion as per agreement |
25 Aug 2022 |
Expected date of Completion |
31/03/2023 |
Processing Dates
TS Date |
11 Jan 2020 |
Estimate Approval |
08 Jan 2020 |
NIT Approval |
28 Jan 2020 |
Tender Closing |
24 Feb 2020 |
Technichal Pre-Qualification |
04 Mar 2020 |
Price bid opening |
19 May 2020 |
Approval Dates
Workorder Date |
30 Jun 2020 |
NA |
25 Aug 2020 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Alappuzha KIIFB - AE 1 |
Date: 02/05/2024 |
Work in progress | 99% Completed
Construction of 35MLD WTP and allied works completed. The trial running and commissioning will be done after getting a power connection. The work for dedicated power connection to WTP and Intake well completed..
Alappuzha KIIFB - AE 1 |
Date: 30/04/2024 |
Work in progress | 99% Completed
Construction of 35MLD WTP and allied works completed. The trial running and commissioning will be done after getting a power connection. The work for dedicated power connection to WTP and Intake well completed..