Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

KIIFB-WSS to Ala, Puliyoor, Budhanoor, Pandanad, Mulakkuzha, Venmony Panchayaths and Chengannur Municipality-Package I

Project KIIFB-WSS to Ala, Puliyoor, Budhanoor, Pandanad, Mulakkuzha, Venmony Panchayaths and Chengannur Municipality-Package I
Project Code ALPKIIFB0919495P1
Type Package
Main Project KIIFB-WSS to Ala, Puliyoor, Budhanoor, Pandanad, Mulakkuzha, Venmony Panchayaths and Chengannur Municipality
Funding Agency KIIFB
Category KIIFB WATER SUPPLY SCHEME
Type of scheme Water Supply
Scheme KIIFB
Description Construction of 35 MLD Water Treatment Plant with parallel plate clarifier, Renovation to existing Intake well cum Pump house -10 m Dia and Intake arrangements, Supply and laying Raw water Pumping main -700 DI K9 - 3050m Construction of OHSR 14.00 LL Capacity and 14.60 LL Sump cum Pump house at WTP, , Supply and erection testing and commissioning of raw water pump sets 270 HP VT 3 nos and Supply and erection testing commissioning of clear water pump set 75 HP CF-5 numbers, 25 HP CF-2 numbers, at clear water Sump, Substation and Transformer at intake pump house Kolamukkam, Design Supply, Erection, Testing and Commissioning of one No.750 KVA, 11 KV/3.30 K V Indoor Transformers and connected works at Raw Water Pump House, Kolamukkam, Substation and Transformer at WTP, Nikarumpuram Design, Supply, Erection, Testing and Commissioning of One Nos.400 KVA, 11 KV/433 V Indoor Transformers and connected works at WTP, Road Restoration works and allied works.
Status On-going
District Alappuzha
Executing Office KIIFB Projects (ALP)
Agreement Number
Agreement Date
TS Amount (Rs) 388811875
TS Number TS/2019-2020/2020/569
Technical specification 35 MLD Water Treatment Plant with parallel plate clarifier Raw water Pumping main -700 DI K9 - 3050m CWPM/CWGM - 400mm DI K9 pipe-380m, 350 mm DI K9 pipe-110m, 160 mm PVC 10 Kg pipe-1560m, 110 mm PVC 10 Kg pipe-2180m, 90 mm PVC 10 Kg pipe-740m, 75 mm PVC 10 Kg pipe-170m Construction of OHSR 14.00 LL Capacity and 14.60 LL Sump cum Pump house at WTP Raw water pump sets - 270 HP VT 3 nos Clear water pump set - 75 HP CF-5 numbers, 25 HP CF-2 numbers.
Contractor M/s Chicago constructions International pvt ltd (Mob: 9447770536)

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
30 Nov 2021 Pending Pending Road Cut Related Risk PWD permission not obtained No comments available. Pending

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 19/10/2020
Scheduled date of Completion as per agreement 25 Aug 2022
Expected date of Completion 31/03/2023

Processing Dates

TS Date 11 Jan 2020
Estimate Approval 08 Jan 2020
NIT Approval 28 Jan 2020
Tender Closing 24 Feb 2020
Technichal Pre-Qualification 04 Mar 2020
Price bid opening 19 May 2020

Approval Dates

Workorder Date 30 Jun 2020
NA 25 Aug 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Alappuzha KIIFB - AE 1
Date: 02/05/2024

Work in progress | 99% Completed

Construction of 35MLD WTP and allied works completed. The trial running and commissioning will be done after getting a power connection. The work for dedicated power connection to WTP and Intake well completed..

Alappuzha KIIFB - AE 1
Date: 30/04/2024

Work in progress | 99% Completed

Construction of 35MLD WTP and allied works completed. The trial running and commissioning will be done after getting a power connection. The work for dedicated power connection to WTP and Intake well completed..