- Home
- KIIFB-WSS to Ala, Puliyoor, Budhanoor, P...
KIIFB-WSS to Ala, Puliyoor, Budhanoor, Pandanad, Mulakkuzha, Venmony Panchayaths and Chengannur Municipality-Package II
Project |
KIIFB-WSS to Ala, Puliyoor, Budhanoor, Pandanad, Mulakkuzha, Venmony Panchayaths and Chengannur Municipality-Package II |
Project Code |
ALPKIIFB0919495P2 |
Type |
Package |
Main Project |
KIIFB-WSS to Ala, Puliyoor, Budhanoor, Pandanad, Mulakkuzha, Venmony Panchayaths and Chengannur Municipality
|
Funding Agency |
KIIFB |
Category |
KIIFB WATER SUPPLY SCHEME |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
Supplying and laying CWPM from Sump (S1) at WTP to OHSR(R1) at Malayil-400mm DI K9-2250m, Construction of 15LL capacity OHSR (R1) at Malayil,Supplying and laying distribution line at Chengannoor municipality Zone 1 t0 4-152km, Railway push through work at RUB Chengannoor |
Status |
On-going |
District |
Alappuzha |
Executing Office |
KIIFB Projects (ALP) |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
630540000 |
TS Number |
TS/2020-2021/2020/26214 |
Technical specification |
CWPM from Sump (S1) at WTP to OHSR(R1) at Malayil-400mm DI K9-2250m
Construction of 15LL capacity OHSR (R1) at Malayil
Supplying and laying distribution line at Chengannoor municipality Zone 1 t0 4-190km
Railway push through work at RUB Chengannoor |
Contractor |
M/s SURYA INTERNATIONAL ENTERPRISE PVT LTD (Mob: 9439525334) |
No project review have been added to this project
Reported Issues
Issue date |
Solved On |
Action Taken On |
Category |
Description |
Comments |
Issue Status |
10 Jan 2022 |
Pending |
24 Jan 2022 |
Contract Related Risks |
Construction of 15 LL OHSR at Malayil, Chengannur Municipality not started |
No comments added. |
Action Taken |
01 Oct 2021 |
Pending |
Pending |
Road Cut Related Risk |
Road cutting permission from KSTP is required for laying pipe in MC road. The road is under DLP |
No comments available. |
Pending |
01 Oct 2021 |
Pending |
Pending |
Road Cut Related Risk |
Delay in laying pipes in PWD roads |
No comments available. |
Pending |
01 Sep 2021 |
Pending |
24 Sep 2021 |
Approval/Permissions Related (from other departments excluding road cut permission and land related) |
Permission from railway is required for Pipeline crossing at km 92/800-900 between Thiruvalla and Chengannoor stations. |
No comments added. |
Action Taken |
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
02/07/2021 |
Scheduled date of Completion as per agreement |
01 Jan 2023 |
Expected date of Completion |
30/06/2023 |
Processing Dates
TS Date |
22 Nov 2020 |
Estimate Approval |
21 Nov 2020 |
NIT Approval |
25 Nov 2020 |
Tender Closing |
10 Feb 2021 |
Technichal Pre-Qualification |
17 Feb 2021 |
Price bid opening |
27 Feb 2021 |
Approval Dates
Workorder Date |
04 May 2021 |
NA |
02 Jul 2021 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Alappuzha KIIFB - AE 1 |
Date: 03/05/2024 |
Work in progress | 34% Completed
Concreting of raft foundation for OHSR is completed on 12/7/2022. Column concreting up to the plinth level is completed. Plinth beam concrete was completed on 1/06/2023. Column up to second brace level completed. The second level brace beam concreting completed. Kodiyettukara railway under passage 400/250mm MS Pipe laying completed. Pipe laying- 110mm PVC pipe 11164m laid, 160mm PVC pipeline 13401m, and 90mm PVC pipe 7251m laid. 250 mm DI Pipe 444m laid. 200 mm DI Pipe 446 m laid. (Total laid length=32706m)..
Alappuzha KIIFB - AE 1 |
Date: 02/05/2024 |
Work in progress | 34% Completed
Concreting of raft foundation for OHSR is completed on 12/7/2022. Column concreting up to the plinth level is completed. Plinth beam concrete was completed on 1/06/2023. Column up to second brace level completed. The second level brace beam concreting completed. Kodiyettukara railway under passage 400/250mm MS Pipe laying completed. Pipe laying- 110mm PVC pipe 11164m laid, 160mm PVC pipeline 13401m, and 90mm PVC pipe 7251m laid. 250 mm DI Pipe 444m laid. 200 mm DI Pipe 446 m laid. (Total laid length=32706m)..