Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

KIIFB-WSS to Ala, Puliyoor, Budhanoor, Pandanad, Mulakkuzha, Venmony Panchayaths and Chengannur Municipality-Package II

Project KIIFB-WSS to Ala, Puliyoor, Budhanoor, Pandanad, Mulakkuzha, Venmony Panchayaths and Chengannur Municipality-Package II
Project Code ALPKIIFB0919495P2
Type Package
Main Project KIIFB-WSS to Ala, Puliyoor, Budhanoor, Pandanad, Mulakkuzha, Venmony Panchayaths and Chengannur Municipality
Funding Agency KIIFB
Category KIIFB WATER SUPPLY SCHEME
Type of scheme Water Supply
Scheme KIIFB
Description Supplying and laying CWPM from Sump (S1) at WTP to OHSR(R1) at Malayil-400mm DI K9-2250m, Construction of 15LL capacity OHSR (R1) at Malayil,Supplying and laying distribution line at Chengannoor municipality Zone 1 t0 4-152km, Railway push through work at RUB Chengannoor
Status On-going
District Alappuzha
Executing Office KIIFB Projects (ALP)
Agreement Number
Agreement Date
TS Amount (Rs) 630540000
TS Number TS/2020-2021/2020/26214
Technical specification CWPM from Sump (S1) at WTP to OHSR(R1) at Malayil-400mm DI K9-2250m Construction of 15LL capacity OHSR (R1) at Malayil Supplying and laying distribution line at Chengannoor municipality Zone 1 t0 4-190km Railway push through work at RUB Chengannoor
Contractor M/s SURYA INTERNATIONAL ENTERPRISE PVT LTD (Mob: 9439525334)

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
10 Jan 2022 Pending 24 Jan 2022 Contract Related Risks Construction of 15 LL OHSR at Malayil, Chengannur Municipality not started No comments added. Action Taken
01 Oct 2021 Pending Pending Road Cut Related Risk Road cutting permission from KSTP is required for laying pipe in MC road. The road is under DLP No comments available. Pending
01 Oct 2021 Pending Pending Road Cut Related Risk Delay in laying pipes in PWD roads No comments available. Pending
01 Sep 2021 Pending 24 Sep 2021 Approval/Permissions Related (from other departments excluding road cut permission and land related) Permission from railway is required for Pipeline crossing at km 92/800-900 between Thiruvalla and Chengannoor stations. No comments added. Action Taken

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 02/07/2021
Scheduled date of Completion as per agreement 01 Jan 2023
Expected date of Completion 30/06/2023

Processing Dates

TS Date 22 Nov 2020
Estimate Approval 21 Nov 2020
NIT Approval 25 Nov 2020
Tender Closing 10 Feb 2021
Technichal Pre-Qualification 17 Feb 2021
Price bid opening 27 Feb 2021

Approval Dates

Workorder Date 04 May 2021
NA 02 Jul 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Alappuzha KIIFB - AE 1
Date: 03/05/2024

Work in progress | 34% Completed

Concreting of raft foundation for OHSR is completed on 12/7/2022. Column concreting up to the plinth level is completed. Plinth beam concrete was completed on 1/06/2023. Column up to second brace level completed. The second level brace beam concreting completed. Kodiyettukara railway under passage 400/250mm MS Pipe laying completed. Pipe laying- 110mm PVC pipe 11164m laid, 160mm PVC pipeline 13401m, and 90mm PVC pipe 7251m laid. 250 mm DI Pipe 444m laid. 200 mm DI Pipe 446 m laid. (Total laid length=32706m)..

Alappuzha KIIFB - AE 1
Date: 02/05/2024

Work in progress | 34% Completed

Concreting of raft foundation for OHSR is completed on 12/7/2022. Column concreting up to the plinth level is completed. Plinth beam concrete was completed on 1/06/2023. Column up to second brace level completed. The second level brace beam concreting completed. Kodiyettukara railway under passage 400/250mm MS Pipe laying completed. Pipe laying- 110mm PVC pipe 11164m laid, 160mm PVC pipeline 13401m, and 90mm PVC pipe 7251m laid. 250 mm DI Pipe 444m laid. 200 mm DI Pipe 446 m laid. (Total laid length=32706m)..