KIIFB-WSS to Ala, Puliyoor, Budhanoor, Pandanad, Mulakkuzha, Venmony Panchayaths and Chengannur Municipality ,Package-III
| Project |
KIIFB-WSS to Ala, Puliyoor, Budhanoor, Pandanad, Mulakkuzha, Venmony Panchayaths and Chengannur Municipality ,Package-III |
| Project Code |
ALPKIIFB0919495P3 |
| Type |
Package |
| Main Project |
KIIFB-WSS to Ala, Puliyoor, Budhanoor, Pandanad, Mulakkuzha, Venmony Panchayaths and Chengannur Municipality
|
| Funding Agency |
KIIFB |
| Category |
KIIFB WATER SUPPLY SCHEME |
| Type of scheme |
Water Supply |
| Scheme |
KIIFB |
| Description |
Supplying and laying CWPM from Sump (S1) at WTP to OHSR (R5) at Parachantha and Pennukara - 500mm DI K 9 -4350 m, 450 mm DI K 9 - 2550m & 300 mm DI K 9 - 2270m.
Construction of OHSR (R5) 10.00 LL capacity and 2 LL capacity sump cum pump house at Parachantha.
Supplying and Laying of CWPM from Sump (S2) at Parachantha to OHSR (R7) at Kalarithara - 200 mm DI K 9 - 2400 m.
Supply and Erection of Clear Water Pumpset at Parachantha.
Construction of 6.5 LL capacity OHSR (R7) at Kalarithara.
Construction of 15 LL capacity OHSR (R6) at Pennukkara
Supplying and laying Distribution system at Mulakkuzha Panchayat Zones 5 - 175.0 km
Supplying and laying Distribution system at Venmony Panchayat Zones 6 - 175.0 km
Supplying and laying Distribution system at Mulakkuzha and Venmony Panchayat Zones 7 and 8- 175.0 km
|
| Status |
On-going |
| District |
Alappuzha |
| Executing Office |
KIIFB Projects (ALP) |
| Agreement Number |
|
| Agreement Date |
|
| TS Amount (Rs) |
|
| TS Number |
|
| Technical specification |
CWPM from Sump (S1) at WTP to OHSR (R5) at Parachantha and Pennukara - 500mm DI K 9 -4350 m, 450 mm DI K 9 - 2550m & 300 mm DI K 9 - 2270m.
Construction of OHSR (R5) 10.00 LL capacity and 2 LL capacity sump cum pump house at Parachantha.
CWPM from Sump (S2) at Parachantha to OHSR (R7) at Kalarithara - 200 mm DI K 9 - 2400 m.
Construction of 6.5 LL capacity OHSR (R7) at Kalarithara.
Construction of 15 LL capacity OHSR (R6) at Pennukkara
Distribution system at Mulakkuzha Panchayat Zones 5 - 175.0 km
Distribution system at Venmony Panchayat Zones 6 - 175.0 km
Distribution system at Mulakkuzha and Venmony Panchayat Zones 7 and 8- 175.0 km
|
No project review have been added to this project
Reported Issues
| Issue date |
Solved On |
Action Taken On |
Category |
Description |
Comments |
Issue Status |
| 01 Oct 2021 |
Pending |
Pending |
Road Cut Related Risk |
Even though PWD informed the road restoration amount through portal, the detailed estimate not yet received. In some of the roads, the application is rejected stating that the ' road is under DLP'. The application for laying pipes in Kollam – Theni NH is rejected stating that ‘ the road is under DLP’. |
No comments available. |
Pending |
| 01 Sep 2021 |
17 Nov 2021 |
23 Sep 2021 |
Land Related Risk |
For constructing OHSR at Kalarithara (Mulakkuzha Panchayat), land (20 cents) has to be handed over by Panchayath. For constructing OHSR at Pennukkara (Ala Panchayat), the Ayurvedic hospital working at proposed OHSR site has to be shifted. |
Resolution from Mulakkuzha Panchayat Obtained |
Solved |
|
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
| Date of start of Package |
Date is not specified |
| Scheduled date of Completion as per agreement |
01 Jan 2026 |
| Expected date of Completion |
30/06/2023 |
Approval Dates
| Workorder Date |
14 Jun 2024 |
| NA |
08 Jul 2024 |
Other details
| Project Schedule |
View |
| Project Components |
View |
| Project Officers |
View |
| Alappuzha KIIFB - AE 1 |
| Date: 23/10/2026 |
Work in progress | 63% Completed
Agreement executed on 08.07.2024(Chicago Constructions International Pvt. Ltd.). Original TOC of the work up to 31.08.2026. Parachantha OHSR(10LL)- Tank concrete completed. Plastering work is in progress.. Kalarithara OHSR (6.5LL) – Tank construction completed. Mulakkuzha pt- Pipe laying progressing (uPVC- 90mm- 62233.63m/77521m, 110mm- 50468.77m/59351m, 160mm- 21675.00m/26098m, 200mm DI– 6707.32m/8250m, 250mm DI– 914.35m/1265m, 300mm DI– 2666.40m/3141.00m, 400mm DI– 1170.28m/1799.00m, 450mm DI– 2679.83m/3302.00m, 500mm DI– 3777.30m/4322m.Total- 152292.88m/185210m). Road restoration progressing. House connection completed- 722nos..
| Alappuzha KIIFB - AE 1 |
| Date: 17/10/2026 |
Work in progress | 63% Completed
Agreement executed on 08.07.2024(Chicago Constructions International Pvt. Ltd.). Original TOC of the work up to 31.08.2026. Parachantha OHSR(10LL)- Tank concrete completed. Plastering work is in progress.. Kalarithara OHSR (6.5LL) – Tank construction completed. Mulakkuzha pt- Pipe laying progressing (uPVC- 90mm- 62233.63m/77521m, 110mm- 50468.77m/59351m, 160mm- 21675.00m/26098m, 200mm DI– 6707.32m/8250m, 250mm DI– 914.35m/1265m, 300mm DI– 2666.40m/3141.00m, 400mm DI– 1170.28m/1799.00m, 450mm DI– 2679.83m/3302.00m, 500mm DI– 3777.30m/4322m.Total- 152292.88m/185210m). Road restoration progressing. House connection completed- 722nos..