Project | Jal Jeevan Mission (JJM)-Laying pipelines for supply improvement in Kattakambal panchayath work II-250mm Dia DI K9 Kattakampal - kurissu to Pazhanji church - General Civil Work |
---|---|
Project Code | TCRJJM022213572P5 |
Type | Package |
Main Project | Jal Jeevan Mission (JJM)-Laying pipe lines for supply improvement in Kattakambal Panchayath - Phase 2- SLSSC-5th-Part-1-Pipeline Work |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Jal Jeevan Mission (JJM)-Laying pipelines for supply improvement in Kattakambal panchayath work II-250mm Dia DI K9 Kattakampal - kurissu to Pazhanji church - General Civil Work |
Status | On-going |
District | Thrissur |
Executing Office | Kunnamkulam Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 9000000 |
TS Number | WRD/KWA-CE(CR)/EST_TS/18718/2023_5_1_1 Dated: 03-08-2023 |
Technical specification | Laying pipelines for supply improvement in Kattakambal panchayath work II-250mm Dia DI K9 Kattakampal - kurissu to Pazhanji church - General Civil Work |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 12/10/2023 |
---|---|
Scheduled date of Completion as per agreement | 11 Mar 2024 |
Expected date of Completion | 31/07/2024 |
TS Date | 03 Aug 2023 |
---|---|
Estimate Approval | 03 Aug 2023 |
NIT Approval | 16 Aug 2023 |
Tender Closing | 22 Aug 2023 |
Technichal Pre-Qualification | 22 Aug 2023 |
Price bid opening | 23 Aug 2023 |
Workorder Date | 12 Oct 2023 |
---|---|
NA | 25 Oct 2023 |
Kunnamkulam PH Sn - AE |
Date: 27/06/2024 |
Work in progress | 50% Completed
Work ongoing pipe laying progress. .
Kunnamkulam PH Sn - AE |
Date: 24/06/2024 |
Work in progress | 50% Completed
Work ongoing pipe laying progress. .