Jal Jeevan Mission (JJM)-Laying pipelines for supply improvement in Kattakambal panchayath-250mm Dia DI K9 Kattakampal village office to Chirakkal centre-General Civil Work-1

Project Jal Jeevan Mission (JJM)-Laying pipelines for supply improvement in Kattakambal panchayath-250mm Dia DI K9 Kattakampal village office to Chirakkal centre-General Civil Work-1
Project Code TCRJJM022213572P7
Type Package
Main Project Jal Jeevan Mission (JJM)-Laying pipe lines for supply improvement in Kattakambal Panchayath - Phase 2- SLSSC-5th-Part-1-Pipeline Work
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-Laying pipelines for supply improvement in Kattakambal panchayath-250mm Dia DI K9 Kattakampal village office to Chirakkal centre-General Civil Work-1
Status On-going
District Thrissur
Executing Office Kunnamkulam Sn
Agreement Number
Agreement Date
TS Amount (Rs) 9000000
TS Number WRD/KWA-CE(CR)/EST_TS/17928/2023_5_2_1 Dated: 01-08-2023
Technical specification Laying pipelines for supply improvement in Kattakambal panchayath-250mm Dia DI K9 Kattakampal village office to Chirakkal centre-General Civil Work-1

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 26/10/2023
Scheduled date of Completion as per agreement 25 Jan 2024
Expected date of Completion 31/07/2024

Processing Dates

TS Date 01 Aug 2023
Estimate Approval 01 Aug 2023
NIT Approval 11 Aug 2023
Tender Closing 18 Aug 2023
Technichal Pre-Qualification 18 Aug 2023
Price bid opening 19 Aug 2023

Approval Dates

Workorder Date 26 Oct 2023
NA 06 Nov 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kunnamkulam PH Sn - AE
Date: 28/06/2024

Work in progress | 30% Completed

Work ongoing.-Laying work completed .Restoration work pending .

Kunnamkulam PH Sn - AE
Date: 27/06/2024

Work in progress | 30% Completed

Work ongoing.-Laying work completed .Restoration work pending .