Jal Jeevan Mission (JJM)-Laying Pipe lines for supply improvement in Kattakambal Panchayath-Work V-Supplying and Laying 200mm DI K9 pipe and 160mm PVC Pipe from Chirakkal Centre to Pengamuk Road,chirakkal centre to Vaykadavu Road-General Civil Work

Project Jal Jeevan Mission (JJM)-Laying Pipe lines for supply improvement in Kattakambal Panchayath-Work V-Supplying and Laying 200mm DI K9 pipe and 160mm PVC Pipe from Chirakkal Centre to Pengamuk Road,chirakkal centre to Vaykadavu Road-General Civil Work
Project Code TCRJJM022213572P2
Type Package
Main Project Jal Jeevan Mission (JJM)-Laying pipe lines for supply improvement in Kattakambal Panchayath - Phase 2- SLSSC-5th-Part-1-Pipeline Work
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-Laying Pipe lines for supply improvement in Kattakambal Panchayath-Work V-Supplying and Laying 200mm DI K9 pipe and 160mm PVC Pipe from Chirakkal Centre to Pengamuk Road,chirakkal centre to Vaykadavu Road-General Civil Work
Status On-going
District Thrissur
Executing Office Kunnamkulam Sn
Agreement Number
Agreement Date
TS Amount (Rs) 10000000
TS Number WRD/KWA-CE(CR)/EST_TS/19023/2023_5_1_1 Dated: 08-08-2023
Technical specification Supplying and Laying 200mm DI K9 pipe and 160mm PVC Pipe from Chirakkal Centre to Pengamuk Road,chirakkal centre to Vaykadavu Road-General Civil Work

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 22/08/2023
Scheduled date of Completion as per agreement 21 Nov 2023
Expected date of Completion 31/07/2024

Processing Dates

TS Date 08 Aug 2023
Estimate Approval 08 Aug 2023
NIT Approval 09 Aug 2023
Tender Closing 16 Aug 2023
Technichal Pre-Qualification 16 Aug 2023
Price bid opening 17 Aug 2023

Approval Dates

Workorder Date 22 Aug 2023
NA 12 Sep 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kunnamkulam PH Sn - AE
Date: 28/06/2024

Work in progress | 50% Completed

2329 M laid out of 4637m . pipe line work in progress. 3rd and part bill scrutiny at division. Final bill under preparation .

Kunnamkulam PH Sn - AE
Date: 27/06/2024

Work in progress | 40% Completed

2329 M laid out of 4637m . pipe line work in progress. 3rd and part bill scrutiny at division. Final bill under preparation .