Jal Jeevan Mission (JJM)-Laying Pipe lines for supply improvement in Kattakambal Panchayath-Work V-Supplying and Laying 200mm DI K9 pipe and 160mm PVC Pipe from Chirakkal Centre to Pengamuk Road,chirakkal centre to Vaykadavu Road-General Civil Work
Project |
Jal Jeevan Mission (JJM)-Laying Pipe lines for supply improvement in Kattakambal Panchayath-Work V-Supplying and Laying 200mm DI K9 pipe and 160mm PVC Pipe from Chirakkal Centre to Pengamuk Road,chirakkal centre to Vaykadavu Road-General Civil Work |
Project Code |
TCRJJM022213572P2 |
Type |
Package |
Main Project |
Jal Jeevan Mission (JJM)-Laying pipe lines for supply improvement in Kattakambal Panchayath - Phase 2- SLSSC-5th-Part-1-Pipeline Work
|
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jal Jeevan Mission (JJM)-Laying Pipe lines for supply improvement in Kattakambal Panchayath-Work V-Supplying and Laying 200mm DI K9 pipe and 160mm PVC Pipe from Chirakkal Centre to Pengamuk Road,chirakkal centre to Vaykadavu Road-General Civil Work |
Status |
On-going |
District |
Thrissur |
Executing Office |
Kunnamkulam Sn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
10000000 |
TS Number |
WRD/KWA-CE(CR)/EST_TS/19023/2023_5_1_1 Dated: 08-08-2023 |
Technical specification |
Supplying and Laying 200mm DI K9 pipe and 160mm PVC Pipe from Chirakkal Centre to Pengamuk Road,chirakkal centre to Vaykadavu Road-General Civil Work |
No project review have been added to this project
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
22/08/2023 |
Scheduled date of Completion as per agreement |
21 Nov 2023 |
Expected date of Completion |
31/07/2024 |
Processing Dates
TS Date |
08 Aug 2023 |
Estimate Approval |
08 Aug 2023 |
NIT Approval |
09 Aug 2023 |
Tender Closing |
16 Aug 2023 |
Technichal Pre-Qualification |
16 Aug 2023 |
Price bid opening |
17 Aug 2023 |
Approval Dates
Workorder Date |
22 Aug 2023 |
NA |
12 Sep 2023 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Kunnamkulam PH Sn - AE |
Date: 28/06/2024 |
Work in progress | 50% Completed
2329 M laid out of 4637m . pipe line work in progress. 3rd and part bill scrutiny at division. Final bill under preparation
.
Kunnamkulam PH Sn - AE |
Date: 27/06/2024 |
Work in progress | 40% Completed
2329 M laid out of 4637m . pipe line work in progress. 3rd and part bill scrutiny at division. Final bill under preparation
.