JJM-Phase 2 CWSS to Moopainad, Meppadi and Vythiri Panchayaths in Wayanad District Phase II

Project JJM-Phase 2 CWSS to Moopainad, Meppadi and Vythiri Panchayaths in Wayanad District Phase II
Project Code CLTJJM092111006
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM-Phase 2 CWSS to Moopainad, Meppadi and Vythiri Panchayaths in Wayanad District Phase II
Status On-going
District Wayanad
Executing Office Kozhikode Project Dn
AS Amount (Rs) 2027700000
AS Number G.O.(Rt)No.489/2021/WRD
TS Amount (Rs) 306000000
TS Number WRD/KWA-CE(NR)/EST_TS/1018/2022_5_1_1
Total Bill Submitted (Rs) 30395244
Total Bill Paid (Rs) 30395244
Population Benefitted 89840
Capacity in MLD 35.00
Actual Project Completion Date Date is not specified
Coverage Moopainad, Meppadi and Vythiri Panchayaths
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jal Jeevan Mission (JJM)-CWSS to Moopainad, Meppadi and Vythiri Panchayaths in Wayanad District-Construction of Reservoir, Supplying and Laying CWGM, Distribution system and providing FHTCs in Vythiri Panchayath Kozhikode Project Dn
2 Jal Jeevan Mission (JJM)-JJM-Phase 2 CWSS to Moopainad, Meppadi and Vythiri Panchayaths in Wayanad District Phase II-- Supply, Laying, Testing and Commissioning of Distribution pipe line and Providing FHTC in Meppadi Panchayath, Design,Construction, Testing and Commissioning of 9 LL Capacity GLSR at Britishkunnu, 5 LL Capacity Booster station cum 9 LL Capacity OHSR at Nedumbala in Meppadi Panchayath Supply, Laying Testing and commissioning of Clear water Pumping main and gravity main, from WTP to Nedumbala , from Nedumbala to British Kunnu. And from British kunnu to Chelode estate. Supply, erection and commissioning of 500 KVA transformer and clear water pump sets at Nedumbala-General Civil Work Kozhikode Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
20 Nov 2023 Vythiri GP- Total PE pipe - 105758m / PE Supplied - 87229m / PE Laid - 38509m ;Total DI pipe - 7408m / DI Supplied - 0m / DI Laid - 0m ; Total pipe - 113166 / Total Supplied - 87229/ Total laid - 38509 ; FHTC Total - 4017, HTC given - 280 Kozhikode Project Dn AE4
06 Nov 2023 Vythiri GP- Total PE pipe - 105758m / PE Supplied - 77229m / PE Laid - 33691m ;Total DI pipe - 7408m / DI Supplied - 0m / DI Laid - 0m ; Total pipe - 113166 / Total Supplied - 77229 / Total laid - 33691 ; FHTC Total - 4017, HTC given - 220 Kozhikode Project Dn AE4
26 Oct 2023 Vythiri GP- Total PE pipe - 105758m / PE Supplied - 77229m / PE Laid - 28841m ;Total DI pipe - 7408m / DI Supplied - 0m / DI Laid - 0m ; Total pipe - 113166 / Total Supplied - 77229 / Total laid - 28841 ; FHTC Total - 4017, HTC given - 110 Kozhikode Project Dn AE4
02 Oct 2023 Vythiri GP- Total PE pipe - 105758m / PE Supplied - 40400m / PE Laid - 3870m ;Total DI pipe - 7408m / DI Supplied - 0m / DI Laid - 0m ; Total pipe - 113166 / Total Supplied - 40400 / Total laid - 4000 ; FHTC Total - 4017, HTC given - 0 Kozhikode Project Dn AE4
23 Sep 2023 Vythiri GP- Total PE pipe - 105758m / PE Supplied - 15800m / PE Laid - 2870m ;Total DI pipe - 7408m / DI Supplied - 0m / DI Laid - 0m ; Total pipe - 113166 / Total Supplied - 15800 / Total laid - 2870 ; FHTC Total - 4017, HTC given - 0 Kozhikode Project Dn AE4

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 22/03/2023
Scheduled date of Completion of the Project 07 Mar 2024
Expected date of Completion 31/03/2024

Processing Dates

AS Date 18 Sep 2021
TS Date 16 Nov 2022

Other details

Project Officers View