Project | Jal Jeevan Mission (JJM)-CWSS to Moopainad, Meppadi and Vythiri Panchayaths in Wayanad District-Construction of Reservoir, Supplying and Laying CWGM, Distribution system and providing FHTCs in Vythiri Panchayath |
---|---|
Project Code | CLTJJM092111006P1 |
Type | Package |
Main Project | JJM-Phase 2 CWSS to Moopainad, Meppadi and Vythiri Panchayaths in Wayanad District Phase II |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-01 |
Description | Construction of Reservoir, Supplying and Laying CWGM, Distribution system and providing FHTCs in Vythiri Panchayath |
Status | On-going |
District | Wayanad |
Executing Office | Kozhikode Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 306000000 |
TS Number | WRD/KWA-CE(NR)/EST_TS/1018/2022_5_1_1 |
Technical specification | Total numbers of FHTCs 4017, 9 LL OHSR at chelode estate ,1 LL GLSR at narikkodumukku |
Contractor | T ABDUSSAMAD (Mob: 9745850000) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 22/03/2023 |
---|---|
Scheduled date of Completion as per agreement | 07 Mar 2024 |
Expected date of Completion | 31/12/2024 |
TS Date | 16 Nov 2022 |
---|---|
Estimate Approval | 16 Nov 2022 |
Tender Closing | 10 Jan 2023 |
Price bid opening | 11 Jan 2023 |
Workorder Date | 08 Mar 2023 |
---|---|
NA | 22 Mar 2023 |
Kozhikode Project Dn AE4 |
Date: 02/03/2025 |
Work in progress | 77% Completed
Total PE pipe - 105758m / PE Supplied - 105293 m / PE Laid - 69096 m ;Total DI pipe - 7408m / DI Supplied - 4167.50 m / DI Laid -687.5 m ; Total pipe - 113166 / Total Supplied - 109460.5 / Total laid - 69783.5 ; FHTC Total - 4017, HTC given - 1936.Earth work excavation completed,levellimg of retaining wall ,PCC of shear key and shuttering and steel work of shear key ,RCC of shear key and Levelling ,and pcc of toe completed .steel work of toe of wall completed .RCC work ,shuttering work completed.Retaining wall concrete completed upto 5 th lift level . earth levelling and pcc done. shear key concrete conducted.Steel work on going ..
Kozhikode Project Dn AE4 |
Date: 01/03/2025 |
Work in progress | 77% Completed
Total PE pipe - 105758m / PE Supplied - 105293 m / PE Laid - 69096 m ;Total DI pipe - 7408m / DI Supplied - 4167.50 m / DI Laid -687.5 m ; Total pipe - 113166 / Total Supplied - 109460.5 / Total laid - 69783.5 ; FHTC Total - 4017, HTC given - 1936.Earth work excavation completed,levellimg of retaining wall ,PCC of shear key and shuttering and steel work of shear key ,RCC of shear key and Levelling ,and pcc of toe completed .steel work of toe of wall completed .RCC work ,shuttering work completed.Retaining wall concrete completed upto 5 th lift level . earth levelling and pcc done. shear key concrete conducted.Steel work on going ..