Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Jal Jeevan Mission (JJM)-CWSS to Moopainad, Meppadi and Vythiri Panchayaths in Wayanad District-Construction of Reservoir, Supplying and Laying CWGM, Distribution system and providing FHTCs in Vythiri Panchayath

Project Jal Jeevan Mission (JJM)-CWSS to Moopainad, Meppadi and Vythiri Panchayaths in Wayanad District-Construction of Reservoir, Supplying and Laying CWGM, Distribution system and providing FHTCs in Vythiri Panchayath
Project Code CLTJJM092111006P1
Type Package
Main Project JJM-Phase 2 CWSS to Moopainad, Meppadi and Vythiri Panchayaths in Wayanad District Phase II
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Construction of Reservoir, Supplying and Laying CWGM, Distribution system and providing FHTCs in Vythiri Panchayath
Status On-going
District Wayanad
Executing Office Kozhikode Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 306000000
TS Number WRD/KWA-CE(NR)/EST_TS/1018/2022_5_1_1
Technical specification Total numbers of FHTCs 4017, 9 LL OHSR at chelode estate ,1 LL GLSR at narikkodumukku
Contractor T ABDUSSAMAD (Mob: 9745850000)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 22/03/2023
Scheduled date of Completion as per agreement 07 Mar 2024
Expected date of Completion 31/12/2024

Processing Dates

TS Date 16 Nov 2022
Estimate Approval 16 Nov 2022
Tender Closing 10 Jan 2023
Price bid opening 11 Jan 2023

Approval Dates

Workorder Date 08 Mar 2023
NA 22 Mar 2023

Other details

Project Schedule View
Project Components View
Project Officers View
Click on Map
Leaflet | © PASK

Project Status Updations See All Status Updations

Kozhikode Project Dn AE4
Date: 02/03/2025

Work in progress | 77% Completed

Total PE pipe - 105758m / PE Supplied - 105293 m / PE Laid - 69096 m ;Total DI pipe - 7408m / DI Supplied - 4167.50 m / DI Laid -687.5 m ; Total pipe - 113166 / Total Supplied - 109460.5 / Total laid - 69783.5 ; FHTC Total - 4017, HTC given - 1936.Earth work excavation completed,levellimg of retaining wall ,PCC of shear key and shuttering and steel work of shear key ,RCC of shear key and Levelling ,and pcc of toe completed .steel work of toe of wall completed .RCC work ,shuttering work completed.Retaining wall concrete completed upto 5 th lift level . earth levelling and pcc done. shear key concrete conducted.Steel work on going ..

Kozhikode Project Dn AE4
Date: 01/03/2025

Work in progress | 77% Completed

Total PE pipe - 105758m / PE Supplied - 105293 m / PE Laid - 69096 m ;Total DI pipe - 7408m / DI Supplied - 4167.50 m / DI Laid -687.5 m ; Total pipe - 113166 / Total Supplied - 109460.5 / Total laid - 69783.5 ; FHTC Total - 4017, HTC given - 1936.Earth work excavation completed,levellimg of retaining wall ,PCC of shear key and shuttering and steel work of shear key ,RCC of shear key and Levelling ,and pcc of toe completed .steel work of toe of wall completed .RCC work ,shuttering work completed.Retaining wall concrete completed upto 5 th lift level . earth levelling and pcc done. shear key concrete conducted.Steel work on going ..