Jal Jeevan Mission (JJM)-Jal Jeevan Mission -Phase 2 CWSS to Moopainad, Meppadi and Vythiri Panchayaths in Wayanad District Phase II-Construction of 11 LL GLSR, Laying Distribution system and providing FHTC in Moopainad Panchayath.-General Civil Work
Project |
Jal Jeevan Mission (JJM)-Jal Jeevan Mission -Phase 2 CWSS to Moopainad, Meppadi and Vythiri Panchayaths in Wayanad District Phase II-Construction of 11 LL GLSR, Laying Distribution system and providing FHTC in Moopainad Panchayath.-General Civil Work |
Project Code |
CLTJJM092111006P3 |
Type |
Package |
Main Project |
JJM-Phase 2 CWSS to Moopainad, Meppadi and Vythiri Panchayaths in Wayanad District Phase II
|
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-01 |
Description |
Construction of 11 LL GLSR, Laying
Distribution system and providing FHTC in Moopainad Panchayath.-General Civil Work |
Status |
On-going |
District |
Wayanad |
Executing Office |
Kozhikode Project Dn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
407000000 |
TS Number |
WRD/KWA-CE(NR)/EST_TS/1869/2022_5_1_1 |
Technical specification |
Construction of 11 LL GLSR, Laying
Distribution system and providing FHTC |
Contractor |
KT.Manoj (Mob: 7558043708) |
No project review have been added to this project
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
25/09/2023 |
Scheduled date of Completion as per agreement |
24 Sep 2024 |
Expected date of Completion |
31/03/2025 |
Processing Dates
TS Date |
06 Dec 2022 |
Estimate Approval |
06 Dec 2022 |
Tender Closing |
02 Jun 2023 |
Price bid opening |
03 Jun 2023 |
Approval Dates
Workorder Date |
19 Aug 2023 |
NA |
15 Sep 2023 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Kozhikode Project Dn AE4 |
Date: 02/03/2025 |
Work in progress | 53% Completed
Total PE pipe - 131902 m / PE Supplied - 130510 m / PE Laid -90381 m ;Total DI pipe - 9840 m / DI Supplied - 0 m / DI Laid -0 m ; Total pipe - 141742 / Total Supplied - 130510 / Total laid - 90381 ; FHTC Total - 7881, HTC given -3788..
Kozhikode Project Dn AE4 |
Date: 01/03/2025 |
Work in progress | 53% Completed
Total PE pipe - 131902 m / PE Supplied - 130510 m / PE Laid -90381 m ;Total DI pipe - 9840 m / DI Supplied - 0 m / DI Laid -0 m ; Total pipe - 141742 / Total Supplied - 130510 / Total laid - 90381 ; FHTC Total - 7881, HTC given -3788..