Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
20 Jan 2025 | Work in progress | Kozhikode Project Dn EE | |
16 Dec 2024 | Work in progress | Kozhikode Project Dn EE | |
13 Nov 2024 | Work in progress | Kozhikode Project Dn AE4 | |
23 Oct 2024 | Work in progress | Kozhikode Project Dn AE4 | |
18 Sep 2024 | Work in progress | Kozhikode Project Dn AE5 | |
01 Aug 2024 | Work in progress | Kozhikode Project Dn AE5 | |
01 Jul 2024 | Work in progress | Kozhikode Project Dn AE5 | |
01 Jun 2024 | Work in progress | Kozhikode Project Dn AE5 | |
20 Nov 2023 | Vythiri GP- Total PE pipe - 105758m / PE Supplied - 87229m / PE Laid - 38509m ;Total DI pipe - 7408m / DI Supplied - 0m / DI Laid - 0m ; Total pipe - 113166 / Total Supplied - 87229/ Total laid - 38509 ; FHTC Total - 4017, HTC given - 280 | Kozhikode Project Dn AE4 | |
06 Nov 2023 | Vythiri GP- Total PE pipe - 105758m / PE Supplied - 77229m / PE Laid - 33691m ;Total DI pipe - 7408m / DI Supplied - 0m / DI Laid - 0m ; Total pipe - 113166 / Total Supplied - 77229 / Total laid - 33691 ; FHTC Total - 4017, HTC given - 220 | Kozhikode Project Dn AE4 |