Jal Jeevan Mission (JJM)-JJM-Phase 2 CWSS to Moopainad, Meppadi and Vythiri Panchayaths in Wayanad District Phase II-- Supply, Laying, Testing and Commissioning of Distribution pipe line and Providing FHTC in Meppadi Panchayath, Design,Construction, Testing and Commissioning of 9 LL Capacity GLSR at Britishkunnu, 5 LL Capacity Booster station cum 9 LL Capacity OHSR at Nedumbala in Meppadi Panchayath Supply, Laying Testing and commissioning of Clear water Pumping main and gravity main, from WTP to Nedumbala , from Nedumbala to British Kunnu. And from British kunnu to Chelode estate. Supply, erection and commissioning of 500 KVA transformer and clear water pump sets at Nedumbala-General Civil Work
Project |
Jal Jeevan Mission (JJM)-JJM-Phase 2 CWSS to Moopainad, Meppadi and Vythiri Panchayaths in Wayanad District Phase II-- Supply, Laying, Testing and Commissioning of Distribution pipe line and Providing FHTC in Meppadi Panchayath, Design,Construction, Testing and Commissioning of 9 LL Capacity GLSR at Britishkunnu, 5 LL Capacity Booster station cum 9 LL Capacity OHSR at Nedumbala in Meppadi Panchayath Supply, Laying Testing and commissioning of Clear water Pumping main and gravity main, from WTP to Nedumbala , from Nedumbala to British Kunnu. And from British kunnu to Chelode estate. Supply, erection and commissioning of 500 KVA transformer and clear water pump sets at Nedumbala-General Civil Work |
Project Code |
CLTJJM092111006P2 |
Type |
Package |
Main Project |
JJM-Phase 2 CWSS to Moopainad, Meppadi and Vythiri Panchayaths in Wayanad District Phase II
|
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-01 |
Description |
Supply, Laying, Testing and Commissioning of Distribution pipe line and Providing FHTC in Meppadi
Panchayath, Design,Construction, Testing and Commissioning of 9 LL Capacity GLSR at Britishkunnu, 5 LL
Capacity Booster station cum 9 LL Capacity OHSR at Nedumbala in Meppadi Panchayath Supply, Laying
Testing and commissioning of Clear water Pumping main and gravity main, from WTP to Nedumbala , from
Nedumbala to British Kunnu. And from British kunnu to Chelode estate. Supply, erection and commissioning of
500 KVA transformer and clear water pump sets at Nedumbala-General Civil Work |
Status |
On-going |
District |
Wayanad |
Executing Office |
Kozhikode Project Dn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
956000000 |
TS Number |
WRD/KWA-CE(NR)/EST_TS/1867/2022_5_5_4 |
Technical specification |
9 LL Capacity GLSR at Britishkunnu, 5 LL
Capacity Booster station cum 9 LL Capacity OHSR at Nedumbala |
No project review have been added to this project
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
15/09/2023 |
Scheduled date of Completion as per agreement |
17 Sep 2024 |
Expected date of Completion |
31/12/2024 |
Processing Dates
TS Date |
11 May 2023 |
Estimate Approval |
11 May 2023 |
Tender Closing |
05 Jun 2023 |
Price bid opening |
06 Jun 2023 |
Approval Dates
Workorder Date |
19 Aug 2023 |
NA |
05 Sep 2023 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Kozhikode Project Dn AE4 |
Date: 02/03/2025 |
Work in progress | 39% Completed
Total DI pipe - 47070 m / DI Supplied - 27858.5 m / DI Laid -8524.9 m ;Total PE pipe - 200602 m / PE Supplied - 71377 m / PE Laid -69432.35 m ; Total pipe - 247672 / Total Supplied - 98962.5 / Total laid -77957.25 ; FHTC Total - 12023, HTC given -1295 , 5LL Booster station cum 9 LL OHSR at Nedumbala - Booster tank - Sump roof slab and roof beam concrete completed &curing completed ,2 nd lift concrete conducted, RW shuttering 3 rd lift concreting conducted ./OHSR- floor slab concrete conducted &curing ongoing and haunch and wall shuttering completed concrete conducted, curing on going ,ohsr column first lift & wall shoe concrete conducted ,side wall first lift concrete conducted ,side wall ,column and stair case concrete conducted,curing on going ,roof beam shuttering work completed,steel work completed & roof slab shuttering completed steel work completed ,stair case shuttering work completed steel work completed /roof slab & stair case concrete conducted ,curing ongoing ./Pump house first lift column concrete completed and 2 nd lift column concrete completed .balance column concrete conducted curing completed ,roof beam steel work completed roof slab concrete completed curing completed . 4 th flight of stair& landing shuttering completed .Main slab concrete completed ,plastering completed ,painting completed,booster tank wall construction completed plastering completed ..
Kozhikode Project Dn AE4 |
Date: 01/03/2025 |
Work in progress | 39% Completed
Total DI pipe - 47070 m / DI Supplied - 27858.5 m / DI Laid -8524.9 m ;Total PE pipe - 200602 m / PE Supplied - 71377 m / PE Laid -69432.35 m ; Total pipe - 247672 / Total Supplied - 98962.5 / Total laid -77957.25 ; FHTC Total - 12023, HTC given -1295 , 5LL Booster station cum 9 LL OHSR at Nedumbala - Booster tank - Sump roof slab and roof beam concrete completed &curing completed ,2 nd lift concrete conducted, RW shuttering 3 rd lift concreting conducted ./OHSR- floor slab concrete conducted &curing ongoing and haunch and wall shuttering completed concrete conducted, curing on going ,ohsr column first lift & wall shoe concrete conducted ,side wall first lift concrete conducted ,side wall ,column and stair case concrete conducted,curing on going ,roof beam shuttering work completed,steel work completed & roof slab shuttering completed steel work completed ,stair case shuttering work completed steel work completed /roof slab & stair case concrete conducted ,curing ongoing ./Pump house first lift column concrete completed and 2 nd lift column concrete completed .balance column concrete conducted curing completed ,roof beam steel work completed roof slab concrete completed curing completed . 4 th flight of stair& landing shuttering completed .Main slab concrete completed ,plastering completed ,painting completed,booster tank wall construction completed plastering completed ..