Jal Jeevan Mission (JJM)-JJM-Phase 2 CWSS to Moopainad, Meppadi and Vythiri Panchayaths in Wayanad District Phase II-- Supply, Laying, Testing and Commissioning of Distribution pipe line and Providing FHTC in Meppadi Panchayath, Design,Construction, Testing and Commissioning of 9 LL Capacity GLSR at Britishkunnu, 5 LL Capacity Booster station cum 9 LL Capacity OHSR at Nedumbala in Meppadi Panchayath Supply, Laying Testing and commissioning of Clear water Pumping main and gravity main, from WTP to Nedumbala , from Nedumbala to British Kunnu. And from British kunnu to Chelode estate. Supply, erection and commissioning of 500 KVA transformer and clear water pump sets at Nedumbala-General Civil Work

Project Jal Jeevan Mission (JJM)-JJM-Phase 2 CWSS to Moopainad, Meppadi and Vythiri Panchayaths in Wayanad District Phase II-- Supply, Laying, Testing and Commissioning of Distribution pipe line and Providing FHTC in Meppadi Panchayath, Design,Construction, Testing and Commissioning of 9 LL Capacity GLSR at Britishkunnu, 5 LL Capacity Booster station cum 9 LL Capacity OHSR at Nedumbala in Meppadi Panchayath Supply, Laying Testing and commissioning of Clear water Pumping main and gravity main, from WTP to Nedumbala , from Nedumbala to British Kunnu. And from British kunnu to Chelode estate. Supply, erection and commissioning of 500 KVA transformer and clear water pump sets at Nedumbala-General Civil Work
Project Code CLTJJM092111006P2
Type Package
Main Project JJM-Phase 2 CWSS to Moopainad, Meppadi and Vythiri Panchayaths in Wayanad District Phase II
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Supply, Laying, Testing and Commissioning of Distribution pipe line and Providing FHTC in Meppadi Panchayath, Design,Construction, Testing and Commissioning of 9 LL Capacity GLSR at Britishkunnu, 5 LL Capacity Booster station cum 9 LL Capacity OHSR at Nedumbala in Meppadi Panchayath Supply, Laying Testing and commissioning of Clear water Pumping main and gravity main, from WTP to Nedumbala , from Nedumbala to British Kunnu. And from British kunnu to Chelode estate. Supply, erection and commissioning of 500 KVA transformer and clear water pump sets at Nedumbala-General Civil Work
Status On-going
District Wayanad
Executing Office Kozhikode Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 956000000
TS Number WRD/KWA-CE(NR)/EST_TS/1867/2022_5_5_4
Technical specification 9 LL Capacity GLSR at Britishkunnu, 5 LL Capacity Booster station cum 9 LL Capacity OHSR at Nedumbala

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 15/09/2023
Scheduled date of Completion as per agreement 17 Sep 2024
Expected date of Completion 31/12/2024

Processing Dates

TS Date 11 May 2023
Estimate Approval 11 May 2023
Tender Closing 05 Jun 2023
Price bid opening 06 Jun 2023

Approval Dates

Workorder Date 19 Aug 2023
NA 05 Sep 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kozhikode Project Dn AE4
Date: 02/03/2025

Work in progress | 39% Completed

Total DI pipe - 47070 m / DI Supplied - 27858.5 m / DI Laid -8524.9 m ;Total PE pipe - 200602 m / PE Supplied - 71377 m / PE Laid -69432.35 m ; Total pipe - 247672 / Total Supplied - 98962.5 / Total laid -77957.25 ; FHTC Total - 12023, HTC given -1295 , 5LL Booster station cum 9 LL OHSR at Nedumbala - Booster tank - Sump roof slab and roof beam concrete completed &curing completed ,2 nd lift concrete conducted, RW shuttering 3 rd lift concreting conducted ./OHSR- floor slab concrete conducted &curing ongoing and haunch and wall shuttering completed concrete conducted, curing on going ,ohsr column first lift & wall shoe concrete conducted ,side wall first lift concrete conducted ,side wall ,column and stair case concrete conducted,curing on going ,roof beam shuttering work completed,steel work completed & roof slab shuttering completed steel work completed ,stair case shuttering work completed steel work completed /roof slab & stair case concrete conducted ,curing ongoing ./Pump house first lift column concrete completed and 2 nd lift column concrete completed .balance column concrete conducted curing completed ,roof beam steel work completed roof slab concrete completed curing completed . 4 th flight of stair& landing shuttering completed .Main slab concrete completed ,plastering completed ,painting completed,booster tank wall construction completed plastering completed ..

Kozhikode Project Dn AE4
Date: 01/03/2025

Work in progress | 39% Completed

Total DI pipe - 47070 m / DI Supplied - 27858.5 m / DI Laid -8524.9 m ;Total PE pipe - 200602 m / PE Supplied - 71377 m / PE Laid -69432.35 m ; Total pipe - 247672 / Total Supplied - 98962.5 / Total laid -77957.25 ; FHTC Total - 12023, HTC given -1295 , 5LL Booster station cum 9 LL OHSR at Nedumbala - Booster tank - Sump roof slab and roof beam concrete completed &curing completed ,2 nd lift concrete conducted, RW shuttering 3 rd lift concreting conducted ./OHSR- floor slab concrete conducted &curing ongoing and haunch and wall shuttering completed concrete conducted, curing on going ,ohsr column first lift & wall shoe concrete conducted ,side wall first lift concrete conducted ,side wall ,column and stair case concrete conducted,curing on going ,roof beam shuttering work completed,steel work completed & roof slab shuttering completed steel work completed ,stair case shuttering work completed steel work completed /roof slab & stair case concrete conducted ,curing ongoing ./Pump house first lift column concrete completed and 2 nd lift column concrete completed .balance column concrete conducted curing completed ,roof beam steel work completed roof slab concrete completed curing completed . 4 th flight of stair& landing shuttering completed .Main slab concrete completed ,plastering completed ,painting completed,booster tank wall construction completed plastering completed ..