JJM 2021-22 - Erumely Panchayath - Phase II
Project |
JJM 2021-22 - Erumely Panchayath - Phase II |
Project Code |
KTMJJM12207016 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Providing new distribution lines in 3 New zones , extension of existing/ongoing distribution lines in 6 zones , Providing 10500 FHTCs. Arranged in 6 packages |
Status |
On-going |
District |
Kottayam |
Executing Office |
Kottayam Project Dn |
AS Amount (Rs) |
588500000
|
AS Number |
G.O.(Rt)No.777/2020/WRD |
TS Amount (Rs) |
436790000 |
TS Number |
TS/2020-20212020/29155 |
Total Bill Submitted (Rs) |
48793773 |
Total Bill Paid (Rs) |
48793773 |
Population Benefitted |
52500 |
Capacity in MLD |
10.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Entire Erumely panchayath. |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
JJM 2020-2021- Phase II - WSS TO ERUMELY PANCHAYATH - KOTTAYAM DISTRICT - PACKAGE - 5 - SUPPLY & LAYING NEW DISTRIBUTION LINES IN ZONE VIII (Distribution from GLSR at Keerithodu) AND PROVIDING FHTC'S |
Kottayam Project Dn |
|
2 |
JJM 2020-2021- Phase II - WSS TO ERUMELY PANCHAYATH - KOTTAYAM DISTRICT - PACKAGE - 6 - SUPPLY & LAYING NEW DISTRIBUTION LINES AND PROVIDING FHTC'S IN ZONE VII (GLSR FROM KANAMALA), DESIGN AND CONSTRUCTION OF NEW BP TANK , SUPPLY & LAYING CONVEYANCE MAIN TO BP TANK, PROVIDING DISTRIBUTION LINES IN ZONE VII(A) FROM BP TANK AND PROVIDING FHTC'S |
Kottayam Project Dn |
|
3 |
JJM 2021-2022- Phase II - WSS TO ERUMELY PANCHAYATH - KOTTAYAM DISTRICT -PACKAGE 4- SUPPLY & LAYING NEW DISTRIBUTION LINES IN ZONE IX (from GLSR at Govindankavala) AND PROVIDING FHTC'S |
Kottayam Project Dn |
|
4 |
JJM 2021-2022--WSS TO ERUMELY-PACKAGE 1-PROVIDING ADDITIONAL DISTRIBUTION LINES /EXTENDING EXISTING DISTRIBUTION LINES IN ZONE II,IV, & V AND PROVIDING FHTC'S |
Kottayam Project Dn |
|
5 |
JJM 2021-2022-WSS TO ERUMELY-PACKAGE 2-PROVIDING ADDITIONAL DISTRIBUTION LINES / EXTENDING EXISTING DISTRIBUTION LINES IN ZONE III (Distribution from GLSR at Karinkallumoozhy) AND PROVIDING FHTCs |
Kottayam Project Dn |
|
6 |
JJM 2021-2022-WSS TO ERUMELY-PACKAGE 3- PROVIDING ADDITIONAL DISTRIBUTION LINES / EXTENDING EXISTING DISTRIBUTION LINES IN ZONE I(Distribution from GLSR at WTP) & VI (Distribution from GLSR at Pallikunnu )AND PROVIDING FHTC'S |
Kottayam Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
05 Nov 2021 |
TS was cancelled for all 6 Packages including the tendered and evaluated one. Estimates are revised to DSOR 2018. Estimates further revised for alternate pipe option as HDPE instead of PVC. Now the Estimate are again revised for provision of restoration on LSGD Roads. Out of 6 Packages 2 are submitted with final revision and 4 are under revision, which shall be submitted by next week. If the LSGD Road cutting provision persists, required AS amount may be doule of prevailing hence new AS is required. |
Meenachal-Malankara Project Dn AEE1 |
|
01 Oct 2021 |
Meeting conducted at PWD EE's chamber on 30-09-2021 with EE Project Division. AEEs and AEs to discuss the issues related with pending road cutting approvals. |
Kottayam AE 3 |
|
10 Sep 2021 |
1 package under tender evaluation. Balance about to cancel and retender after revision with DSR 2018. Revision and comaprisons given for AS revisions required on DSR revision. |
Kottayam Project Dn AE1 |
|
26 Aug 2021 |
1 Package under tender evaluation awaiting rate revision approval. 5 package tender due date over by 24 August and no one participated. |
Kottayam Project Dn AE1 |
|
01 Jun 2021 |
6 packages tendered, Tender evaluation with revised is going on, No work is awarded |
Kottayam Project Dn AE1 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
01/12/2020 |
Scheduled date of Completion of the Project |
28 Feb 2023 |
Expected date of Completion |
31/12/2023 |
Processing Dates
AS Date |
24 Dec 2020 |
TS Date |
22 Jan 2021 |