JJM 2020-2021- Phase II - WSS TO ERUMELY PANCHAYATH - KOTTAYAM DISTRICT - PACKAGE - 5 - SUPPLY & LAYING NEW DISTRIBUTION LINES IN ZONE VIII (Distribution from GLSR at Keerithodu) AND PROVIDING FHTC'S

Project JJM 2020-2021- Phase II - WSS TO ERUMELY PANCHAYATH - KOTTAYAM DISTRICT - PACKAGE - 5 - SUPPLY & LAYING NEW DISTRIBUTION LINES IN ZONE VIII (Distribution from GLSR at Keerithodu) AND PROVIDING FHTC'S
Project Code KTMJJM12207016P5
Type Package
Main Project JJM 2021-22 - Erumely Panchayath - Phase II
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description SUPPLY & LAYING NEW DISTRIBUTION LINES IN ZONE VIII (Distribution from GLSR at Keerithodu) AND PROVIDING FHTC'S
Status On-going
District Kottayam
Executing Office Kottayam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 42090000
TS Number TS/2021-2022/2020/28115
Technical specification SUPPLY & LAYING NEW DISTRIBUTION LINES IN ZONE VIII (Distribution from GLSR at Keerithodu) AND PROVIDING FHTC'S
Contractor JAMES PAUL (Mob: 9447871829)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 18/02/2022
Scheduled date of Completion as per agreement 31 Jul 2022
Expected date of Completion 31/03/2023

Processing Dates

TS Date 10 Dec 2021
Estimate Approval 28 Dec 2021
NIT Approval 11 Jan 2022
Tender Closing 27 Dec 2021
Price bid opening 18 Jan 2022

Approval Dates

NA 18 Feb 2022
Workorder Date 27 Jan 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kottayam Project Dn AE1
Date: 20/12/2023

Work has been completed | 100% Completed

Work Completed.

Kottayam Project Dn AE1
Date: 19/12/2023

Work in progress | 51% Completed

15/17.7 km pipe laid. 80mm GI Interconnection works at Keerithodu progressing. We have to get the road cutting permission from MoRTH =500m (NH 183A). The contractor has to supply the pump sets & PRVs. In order to pump the water from the Kanamala tank to Keerithode tank, the GLSR at Pallikkunnu has to be commissioned .