Project | JJM 2020-2021- Phase II - WSS TO ERUMELY PANCHAYATH - KOTTAYAM DISTRICT - PACKAGE - 5 - SUPPLY & LAYING NEW DISTRIBUTION LINES IN ZONE VIII (Distribution from GLSR at Keerithodu) AND PROVIDING FHTC'S |
---|---|
Project Code | KTMJJM12207016P5 |
Type | Package |
Main Project | JJM 2021-22 - Erumely Panchayath - Phase II |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | SUPPLY & LAYING NEW DISTRIBUTION LINES IN ZONE VIII (Distribution from GLSR at Keerithodu) AND PROVIDING FHTC'S |
Status | On-going |
District | Kottayam |
Executing Office | Kottayam Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 42090000 |
TS Number | TS/2021-2022/2020/28115 |
Technical specification | SUPPLY & LAYING NEW DISTRIBUTION LINES IN ZONE VIII (Distribution from GLSR at Keerithodu) AND PROVIDING FHTC'S |
Contractor | JAMES PAUL (Mob: 9447871829) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 18/02/2022 |
---|---|
Scheduled date of Completion as per agreement | 31 Jul 2022 |
Expected date of Completion | 31/03/2023 |
TS Date | 10 Dec 2021 |
---|---|
Estimate Approval | 28 Dec 2021 |
NIT Approval | 11 Jan 2022 |
Tender Closing | 27 Dec 2021 |
Price bid opening | 18 Jan 2022 |
NA | 18 Feb 2022 |
---|---|
Workorder Date | 27 Jan 2022 |
Kottayam Project Dn AE1 |
Date: 20/12/2023 |
Work has been completed | 100% Completed
Work Completed.
Kottayam Project Dn AE1 |
Date: 19/12/2023 |
Work in progress | 51% Completed
15/17.7 km pipe laid. 80mm GI Interconnection works at Keerithodu progressing. We have to get the road cutting permission from MoRTH =500m (NH 183A). The contractor has to supply the pump sets & PRVs. In order to pump the water from the Kanamala tank to Keerithode tank, the GLSR at Pallikkunnu has to be commissioned .