Project | JJM 2021-2022-WSS TO ERUMELY-PACKAGE 3- PROVIDING ADDITIONAL DISTRIBUTION LINES / EXTENDING EXISTING DISTRIBUTION LINES IN ZONE I(Distribution from GLSR at WTP) & VI (Distribution from GLSR at Pallikunnu )AND PROVIDING FHTC'S |
---|---|
Project Code | KTMJJM12207016P3 |
Type | Package |
Main Project | JJM 2021-22 - Erumely Panchayath - Phase II |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | PROVIDING ADDITIONAL DISTRIBUTION LINES & rider lines / EXTENDING EXISTING DISTRIBUTION LINES IN ZONE I(Distribution from GLSR at WTP) & VI (Distribution from GLSR at Pallikunnu )AND PROVIDING FHTC'S |
Status | On-going |
District | Kottayam |
Executing Office | Kottayam Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 140690000 |
TS Number | TS/2021-2022/2020/28103 |
Technical specification | PROVIDING ADDITIONAL DISTRIBUTION LINES / EXTENDING EXISTING DISTRIBUTION LINES IN ZONE I(Distribution from GLSR at WTP) & VI (Distribution from GLSR at Pallikunnu )AND PROVIDING FHTC'S |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 01/12/2020 |
---|---|
Scheduled date of Completion as per agreement | 12 Sep 2022 |
Expected date of Completion | 31/03/2023 |
TS Date | 11 Dec 2021 |
---|---|
Estimate Approval | 13 Jan 2022 |
NIT Approval | 13 Jan 2022 |
Tender Closing | 03 Feb 2022 |
Price bid opening | 07 Feb 2022 |
Workorder Date | 13 Mar 2022 |
---|---|
NA | 01 Apr 2022 |
Kottayam Proj Dn AE4 |
Date: 26/06/2024 |
Work in progress | 60% Completed
Pipe laying in panchayath and PWD roads are completed. NH 183A permission pending 3 Roads 1. MES plant - Panapilav cheenimaram Road (11km, 350DI K9,300DI K9, 90PE PN-10). 2. MES collage - Chempakapara (6km, 90PE PN-10, 140/cl-5 PVC,160/cl-5 PVC). 3. Peroorthodu - Manjalaruvi Road (0.80km, 250DI K9, 90PE PN-10) 726 (FHTC) 1043 (HTC)-Work Foreclosed .
Kottayam Proj Dn AE4 |
Date: 25/06/2024 |
Work in progress | 55% Completed
Pipe laying in panchayath and PWD roads are completed. NH 183A permission pending 3 Roads 1. MES plant - Panapilav cheenimaram Road (11km, 350DI K9,300DI K9, 90PE PN-10). 2. MES collage - Chempakapara (6km, 90PE PN-10, 140/cl-5 PVC,160/cl-5 PVC). 3. Peroorthodu - Manjalaruvi Road (0.80km, 250DI K9, 90PE PN-10) 726 (FHTC) 1043 (HTC)-Work Foreclosed .