Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
05 Nov 2021 TS was cancelled for all 6 Packages including the tendered and evaluated one. Estimates are revised to DSOR 2018. Estimates further revised for alternate pipe option as HDPE instead of PVC. Now the Estimate are again revised for provision of restoration on LSGD Roads. Out of 6 Packages 2 are submitted with final revision and 4 are under revision, which shall be submitted by next week. If the LSGD Road cutting provision persists, required AS amount may be doule of prevailing hence new AS is required. Meenachal-Malankara Project Dn AEE1
01 Oct 2021 Meeting conducted at PWD EE's chamber on 30-09-2021 with EE Project Division. AEEs and AEs to discuss the issues related with pending road cutting approvals. Kottayam AE 3
10 Sep 2021 1 package under tender evaluation. Balance about to cancel and retender after revision with DSR 2018. Revision and comaprisons given for AS revisions required on DSR revision. Kottayam Project Dn AE1
26 Aug 2021 1 Package under tender evaluation awaiting rate revision approval. 5 package tender due date over by 24 August and no one participated. Kottayam Project Dn AE1
01 Jun 2021 6 packages tendered, Tender evaluation with revised is going on, No work is awarded Kottayam Project Dn AE1
21 May 2021 Estimtes are revised according to new rates Total estimate cost incresed from 46 crores to 52crores. The AS amount is only 49.45 crores Kottayam Project Dn AE1
14 May 2021 Estimate returned from se office, Revised estimate preparation works going on . PWD road restoration request work is going on and joint inspection work with pwd begins Kottayam Project Dn AE1
08 Apr 2021 no tender is awarded Kottayam Project Dn AE1
17 Mar 2021 even after repeated tendering no work is awarded due to non participation Kottayam Project Dn AE1
12 Mar 2021 All six packages retendered and extended Kottayam Project Dn AE1