JJM 2020-2021- Phase II - WSS TO ERUMELY PANCHAYATH - KOTTAYAM DISTRICT - PACKAGE - 6 - SUPPLY & LAYING NEW DISTRIBUTION LINES AND PROVIDING FHTC'S IN ZONE VII (GLSR FROM KANAMALA), DESIGN AND CONSTRUCTION OF NEW BP TANK , SUPPLY & LAYING CONVEYANCE MAIN TO BP TANK, PROVIDING DISTRIBUTION LINES IN ZONE VII(A) FROM BP TANK AND PROVIDING FHTC'S

Project JJM 2020-2021- Phase II - WSS TO ERUMELY PANCHAYATH - KOTTAYAM DISTRICT - PACKAGE - 6 - SUPPLY & LAYING NEW DISTRIBUTION LINES AND PROVIDING FHTC'S IN ZONE VII (GLSR FROM KANAMALA), DESIGN AND CONSTRUCTION OF NEW BP TANK , SUPPLY & LAYING CONVEYANCE MAIN TO BP TANK, PROVIDING DISTRIBUTION LINES IN ZONE VII(A) FROM BP TANK AND PROVIDING FHTC'S
Project Code KTMJJM12207016P6
Type Package
Main Project JJM 2021-22 - Erumely Panchayath - Phase II
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description SUPPLY & LAYING NEW DISTRIBUTION LINES AND PROVIDING FHTC'S IN ZONE VII (GLSR FROM KANAMALA), DESIGN AND CONSTRUCTION OF NEW BP TANK , SUPPLY & LAYING CONVEYANCE MAIN TO BP TANK, PROVIDING DISTRIBUTION LINES IN ZONE VII(A) FROM BP TANK AND PROVIDING FHTC'S
Status On-going
District Kottayam
Executing Office Kottayam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 150190000
TS Number TS/2020-2021/2020/29155
Technical specification SUPPLY & LAYING NEW DISTRIBUTION LINES AND PROVIDING FHTC'S IN ZONE VII (GLSR FROM KANAMALA), DESIGN AND CONSTRUCTION OF NEW BP TANK , SUPPLY & LAYING CONVEYANCE MAIN TO BP TANK, PROVIDING DISTRIBUTION LINES IN ZONE VII(A) FROM BP TANK AND PROVIDING FHTC'S

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 01/12/2020
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion 31/12/2023

Processing Dates

TS Date 25 Jan 2023
Estimate Approval 25 Jan 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kottayam Proj Dn AE4
Date: 26/06/2024

Work has started | 0% Completed

Handover to PH Division for execution .

Kottayam Proj Dn AE4
Date: 25/06/2024

Work has started | 0% Completed

Handover to PH Division for execution .