- Home
- REBUILD-RKI-Implementation of Energy Aud...
REBUILD-RKI-Implementation of Energy Audit Recommendations in North Paravur Pump House -General Civil Work
Project |
REBUILD-RKI-Implementation of Energy Audit Recommendations in North Paravur Pump House -General Civil Work |
Project Code |
EKMRKI082213464 |
Type |
Main project |
Funding Agency |
RKI |
Category |
RKI |
Type of scheme |
Water Supply |
Scheme |
5475-00-115-94-05 |
Description |
REBUILD-RKI-Implementation of Energy Audit Recommendations in North Paravur Pump House -General Civil Work |
Status |
On-going |
District |
Ernakulam |
Executing Office |
Kochi WS Dn |
AS Amount (Rs) |
10000000
|
AS Number |
G.O.(Rt)No.2ggl2022lp&EA |
TS Amount (Rs) |
5900000 |
TS Number |
WRD/KWA-CE(CR)/EST_TS/7663/2022_29_1_1 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
|
Population Benefitted |
|
Capacity in MLD |
|
Actual Project Completion Date |
Date is not specified |
Coverage |
Implementation of Energy Audit Recommendations in North Paravur Pump House |
Packages
No. |
Project Name |
Location |
View |
1 |
REBUILD-KERALA INITIATIVE-(Energy Audit Suggestion) -Supply and erection 630 KVA, 11KV/433 V, 3 Phase, 50 Hz, Copper wound out door type ON cooled transformer having vector group of Dyn 11, Off Circuit tapping +5% to - 7.5% in steps of 2.5%, Bushing on HT & Cable Box LT side and Standard fitting confirming to IS1180 (Level- 2) at North Paravur pump house-General Civil Work |
North Paravoor WS Sn 1 |
|
2 |
REBUILD-RKI-Implementation of Energy Audit Recommendations in North Paravur Pump House -General Civil Work |
North Paravoor WS Sn 1 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
16 Apr 2024 |
The work tendered as per tender no.80/2023-24-due date on 18.3.2024 no offer received. hence date extended Two times.
No offer received |
Kochi WS Dn EE |
|
15 Apr 2024 |
The work tendered on 18.3.2024 no offer received and extended no offer received |
Kochi WS Dn EE |
|
04 Mar 2024 |
Estimate under scrutiny. Awaiting revised AS |
Kochi WS Dn EE |
|
14 Feb 2024 |
Estimate under scrutiny. Awaiting revised AS |
Kochi WS Dn EE |
|
17 Jan 2024 |
awaiting revised AS |
Kochi WS Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
Date is not specified |
Scheduled date of Completion of the Project |
Date is not specified |
Expected date of Completion |
31/08/2024 |
Processing Dates
AS Date |
02 Aug 2022 |
TS Date |
31 Dec 2022 |