| Project | REBUILD-RKI-Implementation of Energy Audit recommendations in North Paravoor pump house-Supply and fixing sluice valve Package-IIB |
|---|---|
| Project Code | EKMRKI082213464P3 |
| Type | Package |
| Main Project | REBUILD-RKI-Implementation of Energy Audit Recommendations in North Paravur Pump House -General Civil Work |
| Funding Agency | RKI |
| Category | RKI |
| Type of scheme | Water Supply |
| Scheme | 5475-00-115-94-05 |
| Description | REBUILD-RKI-Implementation of Energy Audit recommendations in North Paravoor pump house-Supply and fixing sluice valve Package-IIB |
| Status | On-going |
| District | Ernakulam |
| Executing Office | North Paravoor WS Sn 1 |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 22945 |
| TS Number | WRD/KWA-CE(CR)/EST_TS/16319/2024_5_1_1 |
| Technical specification |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 12/08/2024 |
|---|---|
| Scheduled date of Completion as per agreement | Date is not specified |
| Expected date of Completion | 11/11/2024 |
| TS Date | 12 Aug 2024 |
|---|---|
| Estimate Approval | 12 Aug 2024 |
| Kochi WS Dn EE |
| Date: 06/10/2025 |
Work has been completed | 100% Completed
work completed.
| Kochi WS Dn EE |
| Date: 26/09/2025 |
Work has been completed | 100% Completed
work completed.