Status Date |
Overall Project Status |
Project Officer |
Contact |
18 Oct 2024 |
Package -I Transformer work 95% completed, Approval from KEI obtained Charging work pending. Package 2A Replacement of Motor pump house Agreement executed on 27.9.2024. Package 2B Sluice valve Direction given to sub division for arrange the work. Package 2c Solar panel Due to non response work retendered at Sub division Opening date 18.10.2024 |
Kochi WS Dn EE |
|
16 Oct 2024 |
Package -I Transformer work 95% completed, Approval from KEI obtained Charging work pending. Package 2A Replacement of Motor pump house Agreement executed on 27.9.2024. Package 2B Sluice valve Direction given to sub division for arrange the work. Package 2c Solar panel Due to non response work retendered at Sub division Opening date 18.10.2024 |
North Paravoor WS Sn - AE |
|
14 Oct 2024 |
Package -I Transformer work 95% completed, Approval from KEI obtained Charging work pending. Package 2A Replacement of Motor pump house Agreement executed on 27.9.2024. Package 2B Sluice valve Direction given to sub division for arrange the work. Package 2c Solar panel Due to non response work retendered at Sub division Opening date 18.10.2024 |
Kochi WS Dn EE |
|
10 Oct 2024 |
Package -I Transformer work 95% completed, Approval from KEI obtained Charging work pending. Package 2A Replacement of Motor pump house Agreement executed on 27.9.2024. Package 2B Sluice valve Direction given to sub division for arrange the work. Package 2c Solar panel Due to non response work retendered at Sub division Opening date 18.10.2024. |
North Paravoor WS Sn - AE |
|
09 Oct 2024 |
Package -I Transformer work 95% completed, Approval from KEI obtained Charging work pending.
Package 2A Replacement of Motor pump house Agreement executed on 27.9.2024.
Package 2B Sluice valve Direction given to sub division for arrange the work.
Package 2c Solar panel Due to non response work retendered at Sub division Opening date 18.10.2024. |
Kochi WS Dn EE |
|
08 Oct 2024 |
Package -I Transformer work under progress,65% completed Package 2A Replacement of Motor pump house Agreement executed Package 2B Sluice valve Direction given to sub division for arrange the work Package 2c Solar panel Due to non responce work retendered at Sub division |
North Paravoor WS Sn - AE |
|
05 Oct 2024 |
Package -I Transformer work under progress,65% completed Package 2A Replacement of Motor pump house Agreement executed Package 2B Sluice valve Direction given to sub division for arrange the work Package 2c Solar panel Due to non responce work retendered at Sub division |
Kochi WS Dn EE |
|
03 Oct 2024 |
Package -I Transformer work under progress,65% completed Package 2A Replacement of Motor pump house Agreement executed Package 2B Sluice valve Direction given to sub division for arrange the work Package 2c Solar panel Due to non responce work retendered at Sub division |
North Paravoor WS Sn - AE |
|
01 Oct 2024 |
Package -I Transformer work under progress,65% completed
Package 2A Replacement of Motor pump house Agreement executed
Package 2B Sluice valve Direction given to sub division for arrange the work
Package 2c Solar panel Due to non responce work retendered at Sub division
|
Kochi WS Dn EE |
|
30 Sep 2024 |
Package-I work in progress 50& completed Package II A- Work tendered Two offers received Package IIB- direction given to sub division Work arranged in subdivision Package IIC -Due to non response wok re tendered |
North Paravoor WS Sn - AE |
|