| Project | REBUILD-Implementation of Energy Audit Recommendations in North Paravoor pump house-Installation of Solar Power Plant and Yard Lighting-Package- 2C |
|---|---|
| Project Code | EKMRKI082213464P4 |
| Type | Package |
| Main Project | REBUILD-RKI-Implementation of Energy Audit Recommendations in North Paravur Pump House -General Civil Work |
| Funding Agency | RKI |
| Category | RKI |
| Type of scheme | Water Supply |
| Scheme | 5475-00-115-94-05 |
| Description | REBUILD-Implementation of Energy Audit Recommendations in North Paravoor pump house-Installation of Solar Power Plant and Yard Lighting-Package- 2C |
| Status | On-going |
| District | Ernakulam |
| Executing Office | North Paravoor WS Sn 1 |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 805195 |
| TS Number | WRD/KWA-CE(CR)/EST/16323/2024_5_1_1 |
| Technical specification |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 07/08/2024 |
|---|---|
| Scheduled date of Completion as per agreement | Date is not specified |
| Expected date of Completion | 30/11/2024 |
| TS Date | 07 Aug 2024 |
|---|---|
| Estimate Approval | 07 Aug 2024 |
| North Paravoor WS Sn - AE |
| Date: 02/07/2026 |
Work in progress | 0% Completed
Recast Estimate submitted for sanction.
| North Paravoor WS Sn - AE |
| Date: 29/05/2026 |
Work in progress | 0% Completed
Recast Estimate submitted for sanction.