- Home
- REBUILD-KERALA INITIATIVE-(Energy Audit...
REBUILD-KERALA INITIATIVE-(Energy Audit Suggestion) -Supply and erection 630 KVA, 11KV/433 V, 3 Phase, 50 Hz, Copper wound out door type ON cooled transformer having vector group of Dyn 11, Off Circuit tapping +5% to - 7.5% in steps of 2.5%, Bushing on HT & Cable Box LT side and Standard fitting confirming to IS1180 (Level- 2) at North Paravur pump house-General Civil Work
| Project |
REBUILD-KERALA INITIATIVE-(Energy Audit Suggestion) -Supply and erection 630 KVA, 11KV/433 V, 3 Phase, 50 Hz, Copper wound out door type ON cooled transformer having vector group of Dyn 11, Off Circuit tapping +5% to - 7.5% in steps of 2.5%, Bushing on HT & Cable Box LT side and Standard fitting confirming to IS1180 (Level- 2) at North Paravur pump house-General Civil Work |
| Project Code |
EKMRKI082213464P2 |
| Type |
Package |
| Main Project |
REBUILD-RKI-Implementation of Energy Audit Recommendations in North Paravur Pump House -General Civil Work
|
| Funding Agency |
RKI |
| Category |
RKI |
| Type of scheme |
Water Supply |
| Scheme |
5475-00-115-94-05 |
| Description |
REBUILD-KERALA INITIATIVE-(Energy Audit Suggestion) -Supply and erection 630 KVA, 11KV/433 V, 3 Phase, 50 Hz, Copper wound out door type ON cooled transformer having vector group of Dyn 11, Off Circuit tapping +5% to - 7.5% in steps of 2.5%, Bushing on HT & Cable Box LT side and Standard fitting confirming to IS1180 (Level- 2) at North Paravur pump house-General Civil Work |
| Status |
On-going |
| District |
Ernakulam |
| Executing Office |
North Paravoor WS Sn 1 |
| Agreement Number |
|
| Agreement Date |
|
| TS Amount (Rs) |
3800000 |
| TS Number |
WRD/KWA-CE(CR)/EST_TS/8130/2022_29_1_1 |
| Technical specification |
Supply and erection 630 KVA, 11KV/433 V, 3 Phase, 50 Hz, Copper wound out door type ON cooled transformer having vector group of Dyn 11, Off Circuit tapping +5% to - 7.5% in steps of 2.5%, Bushing on HT & Cable Box LT side and Standard fitting confirming to IS1180 |
No project review have been added to this project
|
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
| Date of start of Package |
Date is not specified |
| Scheduled date of Completion as per agreement |
Date is not specified |
| Expected date of Completion |
31/08/2024 |
Processing Dates
| TS Date |
07 Jan 2023 |
| Estimate Approval |
07 Jan 2023 |
| NIT Approval |
31 Jan 2023 |
| Tender Closing |
13 Feb 2023 |
| Price bid opening |
15 Feb 2023 |
Other details
| Project Schedule |
View |
| Project Components |
View |
| Project Officers |
View |
| North Paravoor WS Sn - AE |
| Date: 07/10/2025 |
Work has been completed | 100% Completed
Work completed, bill submitted .
| Kochi WS Dn EE |
| Date: 06/10/2025 |
Work in progress | 95% Completed
Work in progress . 95% Completed.