| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 11 Jul 2023 | Package I - Work completed except electric connection in WTP. Package II - RWPM-37.5 Km pipe laying completed out of 39Km. | Nattika Project Dn | |
| 01 Jul 2023 | Package I - Work completed except electric connection in WTP. Package II - RWPM-37.5 Km pipe laying completed out of 39Km. | Nattika Project Dn | |
| 05 Jun 2023 | Package I - Work completed except electric connection. Package II - RWPM-37 Km pipe laying completed out of 38Km. Works to be completed - Interconnection work Chirakkal bridge crossing, Koombully bridge crossing, Pipe laying from Koombully to Pavaratty, One culvert crossing at Mamabazaar. pipe laying in progress from koombully to pavartty | Nattika Project Dn | |
| 22 May 2023 | Package I - Work completed except electric connection. Package II - RWPM-37 Km pipe laying completed out of 39km. Works to be completed - Interconnection work at HB canal, Chirakkal bridge crossing, Koombully bridge crossing, Pipe laying from Koombully to Pavaratty, One culvert crossing at Mamabazaar. pipe laying in progress from koombully to pavartty | Nattika Proj Dn AEE | |
| 22 May 2023 | Package I - Work completed except electric connection. Package II - RWPM-35 Km pipe laying completed out of 38 km. Works to be completed - Interconnection work at HB canal, Chirakkal bridge crossing, Koombully bridge crossing, Pipe laying from Koombully to Pavaratty, One culvert crossing at Mamabazaar Electric connection work WTP pending 95 | Nattika Project Dn | |
| 08 May 2023 | Package I - Work completed except electric connection. Package II - RWPM-35 Km pipe laying completed out of 38 km. Works to be completed - Interconnection work at HB canal, Chirakkal bridge crossing, Koombully bridge crossing, Pipe laying from Koombully to Pavaratty, One culvert crossing at Mamabazaar Electric connection work WTP pending | Nattika Project Dn | |
| 05 May 2023 | Package I - Work completed except electric connection. Package II - RWPM-35 Km pipe laying completed out of 38 km. Works to be completed - Interconnection work at HB canal, Chirakkal bridge crossing, Koombully bridge crossing, Pipe laying from Koombully to Pavaratty, One culvert crossing at Mamabazaar | Nattika Proj Dn AEE | |
| 11 Apr 2023 | RWPM 35.5 Km completed out of 38 km | Nattika Project Dn | |
| 19 Jan 2023 | RWPM-34Km pipe laying completed out of 38 km. Pavaratty to koobuly bridge, kotapadi to WTP, koobuly bridge crossing ,herbert canal crossing, hp canal crossing road restoration work pending. Work started Chainage 21/100 to 22/100 panjaramuku to mamabazar works started | Nattika Project Dn | |
| 22 Dec 2022 | Phase I - Work completed except electric connection. Phase II - RWPM-32 Km pipe laying completed out of 38 km. Pavaratty to koobuly bridge, kotapadi to WTP, Enamave bride HDPE work, koobuly bridge crossing herbert canal crossing, hp canal crossing road restoration work pending. Work started Chainage 22/100 to 23/010 Palayur church to panjaramuku junction. | Nattika Project Dn |