Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
11 Jul 2023 Package I - Work completed except electric connection in WTP. Package II - RWPM-37.5 Km pipe laying completed out of 39Km. Nattika Project Dn
01 Jul 2023 Package I - Work completed except electric connection in WTP. Package II - RWPM-37.5 Km pipe laying completed out of 39Km. Nattika Project Dn
05 Jun 2023 Package I - Work completed except electric connection. Package II - RWPM-37 Km pipe laying completed out of 38Km. Works to be completed - Interconnection work Chirakkal bridge crossing, Koombully bridge crossing, Pipe laying from Koombully to Pavaratty, One culvert crossing at Mamabazaar. pipe laying in progress from koombully to pavartty Nattika Project Dn
22 May 2023 Package I - Work completed except electric connection. Package II - RWPM-37 Km pipe laying completed out of 39km. Works to be completed - Interconnection work at HB canal, Chirakkal bridge crossing, Koombully bridge crossing, Pipe laying from Koombully to Pavaratty, One culvert crossing at Mamabazaar. pipe laying in progress from koombully to pavartty Nattika Proj Dn AEE
22 May 2023 Package I - Work completed except electric connection. Package II - RWPM-35 Km pipe laying completed out of 38 km. Works to be completed - Interconnection work at HB canal, Chirakkal bridge crossing, Koombully bridge crossing, Pipe laying from Koombully to Pavaratty, One culvert crossing at Mamabazaar Electric connection work WTP pending 95 Nattika Project Dn
08 May 2023 Package I - Work completed except electric connection. Package II - RWPM-35 Km pipe laying completed out of 38 km. Works to be completed - Interconnection work at HB canal, Chirakkal bridge crossing, Koombully bridge crossing, Pipe laying from Koombully to Pavaratty, One culvert crossing at Mamabazaar Electric connection work WTP pending Nattika Project Dn
05 May 2023 Package I - Work completed except electric connection. Package II - RWPM-35 Km pipe laying completed out of 38 km. Works to be completed - Interconnection work at HB canal, Chirakkal bridge crossing, Koombully bridge crossing, Pipe laying from Koombully to Pavaratty, One culvert crossing at Mamabazaar Nattika Proj Dn AEE
11 Apr 2023 RWPM 35.5 Km completed out of 38 km Nattika Project Dn
19 Jan 2023 RWPM-34Km pipe laying completed out of 38 km. Pavaratty to koobuly bridge, kotapadi to WTP, koobuly bridge crossing ,herbert canal crossing, hp canal crossing road restoration work pending. Work started Chainage 21/100 to 22/100 panjaramuku to mamabazar works started Nattika Project Dn
22 Dec 2022 Phase I - Work completed except electric connection. Phase II - RWPM-32 Km pipe laying completed out of 38 km. Pavaratty to koobuly bridge, kotapadi to WTP, Enamave bride HDPE work, koobuly bridge crossing herbert canal crossing, hp canal crossing road restoration work pending. Work started Chainage 22/100 to 23/010 Palayur church to panjaramuku junction. Nattika Project Dn