| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 03 Nov 2022 | Phase I - Work completed except electric connection. Phase II - RWPM-32 Km pipe laying completed out of 38 km. Pavaratty to koobuly bridge, kotapadi to WTP, Enamave bride HDPE work, koobuly bridge crossing herbert canal crossing, hp canal crossing road restoration work pending. Work started Chainage 22/100 to 23/010 Palayur church to panjaramuku junction. | Nattika Project Dn | |
| 01 Nov 2022 | intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 32 km pipe laying completed. Chavakkad Wadakkanchery road pipe line work completed | Nattika Project Dn | |
| 21 Jun 2022 | intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 32 km pipe laying completed. Chavakkad Wadakkanchery road pipe line work completed | Nattika Project Dn | |
| 17 Jun 2022 | intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 32 km pipe laying completed. Chavakkad Wadakkanchery road pipe line work completed | Nattika Project Dn | |
| 14 Jun 2022 | intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 32 km pipe laying completed. Chavakkad Wadakkanchery road pipe line work completed | Nattika Project Dn | |
| 14 Jun 2022 | intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 32 km pipe laying completed. Chavakkad Wadakkanchery road pipe line work completed | Nattika Project Dn | |
| 13 Jun 2022 | intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 32 km pipe laying completed. Chavakkad Wadakkanchery road pipe line work completed | Nattika Project Dn | |
| 10 Jun 2022 | intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 32 km pipe laying completed. Chavakkad Wadakkanchery road pipe line work completed | Nattika Project Dn | |
| 04 Jun 2022 | intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 32 km pipe laying completed. Chavakkad Wadakkanchery road pipe line work completed | Nattika Proj Dn AEE | |
| 03 Jun 2022 | intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 32 km pipe laying completed. Chavakkad Wadakkanchery road pipe line work completed | Nattika Project Dn |