Overall Project Status

Status Date Overall Project Status Project Officer Contact
22 Mar 2022 intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 30 km pipe laying completed Nattika Project Dn
21 Mar 2022 intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 30 km pipe laying completed Nattika Project Dn
19 Mar 2022 intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 30 km pipe laying completed Nattika Project Dn
18 Mar 2022 intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 29 km pipe laying completed Nattika Project Dn
16 Mar 2022 intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 29 km pipe laying completed Nattika Project Dn
15 Mar 2022 intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 29 km pipe laying completed Nattika Project Dn
14 Mar 2022 intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 29 km pipe laying completed Nattika Project Dn
11 Mar 2022 intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 29 km pipe laying completed Nattika Project Dn
10 Mar 2022 intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 29 km pipe laying completed Nattika Project Dn
09 Mar 2022 intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 29 km pipe laying completed Nattika Project Dn