| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 02 Jun 2022 | intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 32 km pipe laying completed. Chavakkad Wadakkanchery road pipe line work completed | Nattika Project Dn | |
| 01 Jun 2022 | intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 32 km pipe laying completed. Chavakkad Wadakkanchery road pipe line work completed | Nattika Project Dn | |
| 31 May 2022 | intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 32 km pipe laying completed. Chavakkad Wadakkanchery road pipe line work completed | Nattika Project Dn | |
| 30 May 2022 | intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 32 km pipe laying completed. Chavakkad Wadakkanchery road pipe line work completed | Nattika Project Dn | |
| 28 May 2022 | intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 32 km pipe laying completed. Chavakkad Wadakkanchery road pipe line work completed | Nattika Project Dn | |
| 27 May 2022 | intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 32 km pipe laying completed. Chavakkad Wadakkanchery road pipe line work completed | Nattika Project Dn | |
| 26 May 2022 | intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 32 km pipe laying completed. Chavakkad Wadakkanchery road pipe line work completed | Nattika Project Dn | |
| 25 May 2022 | intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 32 km pipe laying completed. Chavakkad Wadakkanchery road pipe line work completed | Nattika Project Dn | |
| 24 May 2022 | intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 32 km pipe laying completed. Chavakkad Wadakkanchery road pipe line work completed | Nattika Project Dn | |
| 23 May 2022 | intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 32 km pipe laying completed. Chavakkad Wadakkanchery road pipe line work completed | Nattika Project Dn |