Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
02 Feb 2022 | the second lift of side wall of sump is completed.Also the raw water pumping main of 500 mm dia.is going on.Now the reinfocement works and form work for the top slab of sump is going on. | Thiruvananthapuram Project AE1 | |
01 Feb 2022 | the second lift of side wall of sump is completed.Also the raw water pumping main of 500 mm dia.is going on.Now the reinfocement works and form work for the top slab of sump is going on. | Thiruvananthapuram Project AE1 | |
28 Jan 2022 | the second lift of side wall of sump is completed.Also the raw water pumping main of 500 mm dia.is going on | Thiruvananthapuram Project AE1 | |
26 Jan 2022 | The reinforcement work and the formwork for the second lift of side wall of sump is going on | Thiruvananthapuram Project AE1 | |
23 Jan 2022 | First lift of side wall of sump is completed.Now the reinforcement work and the formwork for the second lift of side wall of sump is going on | Thiruvananthapuram Project AE1 | |
21 Jan 2022 | First lift of side wall of sump is completed | Thiruvananthapuram Project AE1 | |
19 Jan 2022 | Column inside the sump for first lift is completed. | Thiruvananthapuram Project AE1 | |
12 Jan 2022 | haunge concreting of sump is completed | Thiruvananthapuram Project AE1 | |
09 Jan 2022 | Base concrete of sump is completed. | Thiruvananthapuram Project AE1 | |
06 Jan 2022 | PCC work for the sump is completed. Now the reinforcement work for the footing of column of sump and side wall of sump is going on. | Thiruvananthapuram Project AE1 |