Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
15 May 2022 The raw water pumping main of 500 mm dia.is going on and.Also the roof of P H room building is over .foundation work(Piling work) of WTP is completed .PCC work of foundation of Lamella clarifier is completed.Well construction at Pirayumoodu sixth lift of concreting completed . pressure testing for 395 m is conducted on 26.04.2022Plate load test conducted on 14.05.2022 and passed. Thiruvananthapuram Project AE1
11 May 2022 The raw water pumping main of 500 mm dia.is going on and.Also the roof of P H room building is over .foundation work(Piling work) of WTP is completed .PCC work of foundation of Lamella clarifier is completed.Well construction at Pirayumoodu sixth lift of concreting completed . pressure testing for 395 m is conducted on 26.04.2022Arrangements for pile load testing started Thiruvananthapuram Project AE1
08 May 2022 The raw water pumping main of 500 mm dia.is going on and.Also the roof of P H room building is over .foundation work(Piling work) of WTP is completed .PCC work of foundation of Lamella clarifier is completed.Well construction at Pirayumoodu sixth lift of concreting completed . pressure testing for 395 m is conducted on 26.04.2022Arrangements for pile load testing started Thiruvananthapuram Project AE1
08 May 2022 The raw water pumping main of 500 mm dia.is going on and.Also the roof of P H room building is over .foundation work(Piling work) of WTP is completed .PCC work of foundation of Lamella clarifier is completed.Well construction at Pirayumoodu sixth lift of concreting completed . pressure testing for 395 m is conducted on 26.04.2022Arrangements for pile load testing started Thiruvananthapuram Project AE1
05 May 2022 The raw water pumping main of 500 mm dia.is going on and.Also the roof of P H room building is over .foundation work(Piling work) of WTP is completed .PCC work of foundation of Lamella clarifier is completed.Well construction at Pirayumoodu sixth lift of concreting completed . pressure testing for 395 m is conducted on 26.04.2022 Thiruvananthapuram Project AE1
02 May 2022 The raw water pumping main of 500 mm dia.is going on and the thrust block is constructed .Also the roof of substation building is over foundation work(Piling work) of WTP is copleted .Well construction at Pirayumoodu fifth lift of concreting completed . pressure testing is conducted on 26.04.2022 Thiruvananthapuram Project AE1
27 Apr 2022 The raw water pumping main of 500 mm dia.is going on and the thrust block is constructed .Also the roof of substation building is over foundation work(Piling work) of WTP is copleted .Well construction at Pirayumoodu fifth lift of concreting completed . pressure testing is conducted on 26.04.2022 Thiruvananthapuram Project AE1
22 Apr 2022 The raw water pumping main of 500 mm dia.is going on and the thrust block is constructed .Also the roof of substation building is over foundation work(Piling work) of WTP is copleted .Well construction at Pirayumoodu fifth lift of concreting completed .Dummy plate is fixed for pressure testing and the test is going to be done this week Thiruvananthapuram Project AE1
18 Apr 2022 The raw water pumping main of 500 mm dia.is going on and the thrust block is constructed .Also the roof of substation building is over foundation work(Piling work) of WTP is going on.Well construction at Pirayumoodu fifth lift of concreting completed on 07.04.2022.Dummy plate is fixed for pressure testing and the test is going to be done this week Thiruvananthapuram Project AE1
17 Apr 2022 The raw water pumping main of 500 mm dia.is going on and the thrust block is constructed .Also the roof of substation building is over foundation work(Piling work) of WTP is going on.Well construction at Pirayumoodu fifth lift of concreting completed on 07.04.2022. No work on last 3 days. Thiruvananthapuram Project AE1