25 Sep 2021 Soil testing was conducted at WTP site at Pongil on 21-09-21 Thiruvananthapuram Project AE1
24 Sep 2021 Survey work is going on .Request letter for handing over work site for construction of WTP is submitted to the Secretary ,Athiyannoor panchayath and the same is not received till date. Thiruvananthapuram Project AE1
21 Sep 2021 Survey work is going on .Request letter for handing over work site for construction of WTP is submitted to the Secretary ,Athiyannoor panchayath and the same is not received till date. Thiruvananthapuram Project AE1
18 Sep 2021 The work is awarded to the contractor M/sChicago Constructions International (P)Ltd;Sasthamangalam bySE PH Circle,Thiruvananthapuram vide Order No.KWA/PHC-D2/5662/2017 Dated 10/09/2021 Thiruvananthapuram Project AE1
12 Sep 2021 Financial bid documents submitted to higher officials on 03/09/2021 STC-TA to be conducted and tender to be finalised. Thiruvananthapuram Project AE1
08 Sep 2021 Financial bid documents submitted to higher officials on 03/09/2021 STC-TA to be conducted and tender to be finalised. Thiruvananthapuram Project AE1
05 Sep 2021 Financial bid documents submitted to higher officials on 03/09/2021 STC-TA to be conducted and tender to be finalised. Thiruvananthapuram Project AE1
02 Sep 2021 Tender documents & financial details under scrutiny. Thiruvananthapuram Project AE1
27 Aug 2021 Final technical prequalification proceedings uploaded. Financial bid opening is on 31-08-21 Thiruvananthapuram Project AE1
26 Aug 2021 STC TA conducted on CE's Office on 24-08-21 Thiruvananthapuram Project AE1