Overall Project Status

Status Date Overall Project Status Project Officer Contact
03 Mar 2022 The raw water pumping main of 500 mm dia.is going on. The roof concreting of sump completed. .Also foundation work(Piling work) of WTP of is going on.Well construction at Pirayumoodu is progressing Thiruvananthapuram Project AE1
27 Feb 2022 The raw water pumping main of 500 mm dia.is going on. The roof concreting of sump completed. .Also foundation work(Piling work) of WTP of is going on. Thiruvananthapuram Project AE1
26 Feb 2022 The raw water pumping main of 500 mm dia.is going on. The roof concreting of sump completed. .Also foundation work(Piling work) of WTP of is going on. Thiruvananthapuram Project AE1
22 Feb 2022 The raw water pumping main of 500 mm dia.is going on. The roof concreting of sump completed. .Also foundation work(Piling work) of WTP of is going on. Thiruvananthapuram Project AE1
20 Feb 2022 The third lift of side wall of sump is completed .Also the raw water pumping main of 500 mm dia.is going on.The first half of concreting is completed. Now the reinfocement works and form work for the second half of top slab of sump is going on.Also foundation work of WTP of is going on. Thiruvananthapuram Project AE1
17 Feb 2022 the third lift of side wall of sump is completed .Also the raw water pumping main of 500 mm dia.is going on.The first half of concreting is completed. Now the reinfocement works and form work for the second half of top slab of sump is going on. Thiruvananthapuram Project AE1
13 Feb 2022 the third lift of side wall of sump is completed .Also the raw water pumping main of 500 mm dia.is going on. Now the reinfocement works and form work for the top slab of sump is going on. Thiruvananthapuram Project AE1
09 Feb 2022 the third lift of side wall of sump is completed .Also the raw water pumping main of 500 mm dia.is going on. Now the reinfocement works and form work for the top slab of sump is going on. Thiruvananthapuram Project AE1
07 Feb 2022 the third lift of side wall of sump is completed .Also the raw water pumping main of 500 mm dia.is going on. Now the reinfocement works and form work for the top slab of sump is going on. Thiruvananthapuram Project AE1
04 Feb 2022 the third lift of side wall of sump is completed .Also the raw water pumping main of 500 mm dia.is going on. Now the reinfocement works and form work for the top slab of sump is going on. Thiruvananthapuram Project AE1