Status Date Overall Project Status Project Officer Contact
29 Jun 2022 Well construction at Pirayumoodu eleventh lift of concreting iscompleted. and concrete third lift of side wall of floculator and clarifier completed .Pile cap RCC done at Pipe gallery at the WTP site at Pongil. Thiruvananthapuram Project AE1
26 Jun 2022 Well construction at Pirayumoodu eleventh lift of concreting iscompleted.and concrete third lift of side wall of floculator and clarifier completed .Pile cap RCC done at Pipe gallery at the WTP site at Pongil. Thiruvananthapuram Project AE1
23 Jun 2022 Well construction at Pirayumoodu tenth lift of concreting iscompleted..is completed.and third lift of side wall of floculator and clarifier shuttring is going on.Shuttering of Eleventh lift of side wall is going .Pile cap RCC done at Pipe gallery at the WTP site at Pongil. Thiruvananthapuram Project AE1
18 Jun 2022 Well construction at Pirayumoodu tenth lift of concreting iscompleted..is completed.and third lift of side wall of floculator and clarifier shuttring is going on.Shuttering of Eleventh lift of side wall is going .Pile cap RCC done at Pipe gallery at the WTP site at Pongil. Thiruvananthapuram Project AE1
15 Jun 2022 Well construction at Pirayumoodu tenth lift of concreting is going on..Second .Raft footing of Floculator is completed.Pile load test(Initial test) conducted on 29.05.2022. and passed.Pile cap RCC is going today. Thiruvananthapuram Project AE1
02 Jun 2022 Well construction at Pirayumoodu sixth lift of concreting completed . pressure testing for 395 m is conducted on 26.04.2022Plate load test conducted on 14.05.2022 and passed.Second reach of pressure test for a length of 546.82 m conducted on 18.05.2022Raft footing of Floculator is completed.Pile load test(Initial test) conducted on 29.05.2022. and passed Thiruvananthapuram Project AE1
30 May 2022 Well construction at Pirayumoodu sixth lift of concreting completed . pressure testing for 395 m is conducted on 26.04.2022Plate load test conducted on 14.05.2022 and passed.Second reach of pressure test for a length of 546.82 m conducted on 18.05.2022Raft footing of Floculator is completed.Pile load test(Initial test) conducted on 29.05.2022. and passed Thiruvananthapuram Project AE1
26 May 2022 The raw water pumping main of 500 mm dia.is going on and.Also the roof of P H room building is over .foundation work(Piling work) of WTP is completed .PCC work of foundation of Lamella clarifier is completed.Well construction at Pirayumoodu sixth lift of concreting completed . pressure testing for 395 m is conducted on 26.04.2022Plate load test conducted on 14.05.2022 and passed.Second reach of pressure test for a length of 546.82 m conducted on 18.05.2022.Footing of RCC in floculator completed . Thiruvananthapuram Project AE1
22 May 2022 The raw water pumping main of 500 mm dia.is going on and.Also the roof of P H room building is over .foundation work(Piling work) of WTP is completed .PCC work of foundation of Lamella clarifier is completed.Well construction at Pirayumoodu sixth lift of concreting completed . pressure testing for 395 m is conducted on 26.04.2022Plate load test conducted on 14.05.2022 and passed.Second reach of pressure test for a length of 546.82 m conducted on 18.05.2022.Footing of RCC in floculator completed . Thiruvananthapuram Project AE1
19 May 2022 The raw water pumping main of 500 mm dia.is going on and.Also the roof of P H room building is over .foundation work(Piling work) of WTP is completed .PCC work of foundation of Lamella clarifier is completed.Well construction at Pirayumoodu sixth lift of concreting completed . pressure testing for 395 m is conducted on 26.04.2022Plate load test conducted on 14.05.2022 and passed.Second reach of pressure test for a length of 546.82 m conducted on 18.05.2022 Thiruvananthapuram Project AE1