Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
22 Oct 2021 | Site for well cum pump house at Pirayinmoodu and WTP at Pongil are handed over to the firm on 21.10.2021. | Thiruvananthapuram Project AE1 | |
19 Oct 2021 | Inauguration conducted at WTP site ,Pongil on 11.10.2021 by Hon: Minister Sri.ROSHI AGASTIN at 4.00 PM Also soil testing and site clearing is is going on | Thiruvananthapuram Project AE1 | |
16 Oct 2021 | Inauguration conducted at WTP site ,Pongil on 11.10.2021 by Hon: Minister Sri.ROSHI AGASTIN at 4.00 PM Also soil testing is going on | Thiruvananthapuram Project AE1 | |
13 Oct 2021 | Inauguration conducted at WTP site ,Pongil on 11.10.2021 by Hon: Minister Sri.ROSHI AGASTIN at 4.00 PM Also soil testing is going on | Thiruvananthapuram Project AE1 | |
13 Oct 2021 | Inauguration conducted at WTP site ,Pongil on 11.10.2021 by Hon: Minister Sri.ROSHI AGASTIN at 4.00 PM | Thiruvananthapuram Project AE1 | |
12 Oct 2021 | Inauguration conducted at WTP site ,Pongil on 11.10.2021 by Hon: Minister Sri.ROSHI AGASTIN at 4.00 PM | Thiruvananthapuram Project AE1 | |
10 Oct 2021 | Inauguration of the starting of the work is proposed to be conducted on 11.10.2021 at the WTP site ,Pongil by Hon.Minister Water Resources Dept. | Thiruvananthapuram Project AE1 | |
06 Oct 2021 | Soil testing was conducted at WTP site at Pongil on 21-09-21 and Bhoomi pooja conducted at site. | Thiruvananthapuram Project AE1 | |
30 Sep 2021 | Soil testing was conducted at WTP site at Pongil on 21-09-21 and Bhoomi pooja conducted at site. | Thiruvananthapuram Project AE1 | |
27 Sep 2021 | Soil testing was conducted at WTP site at Pongil on 21-09-21 | Thiruvananthapuram Project AE1 |