Overall Project Status

Status Date Overall Project Status Project Officer Contact
22 Oct 2021 Site for well cum pump house at Pirayinmoodu and WTP at Pongil are handed over to the firm on 21.10.2021. Thiruvananthapuram Project AE1
19 Oct 2021 Inauguration conducted at WTP site ,Pongil on 11.10.2021 by Hon: Minister Sri.ROSHI AGASTIN at 4.00 PM Also soil testing and site clearing is is going on Thiruvananthapuram Project AE1
16 Oct 2021 Inauguration conducted at WTP site ,Pongil on 11.10.2021 by Hon: Minister Sri.ROSHI AGASTIN at 4.00 PM Also soil testing is going on Thiruvananthapuram Project AE1
13 Oct 2021 Inauguration conducted at WTP site ,Pongil on 11.10.2021 by Hon: Minister Sri.ROSHI AGASTIN at 4.00 PM Also soil testing is going on Thiruvananthapuram Project AE1
13 Oct 2021 Inauguration conducted at WTP site ,Pongil on 11.10.2021 by Hon: Minister Sri.ROSHI AGASTIN at 4.00 PM Thiruvananthapuram Project AE1
12 Oct 2021 Inauguration conducted at WTP site ,Pongil on 11.10.2021 by Hon: Minister Sri.ROSHI AGASTIN at 4.00 PM Thiruvananthapuram Project AE1
10 Oct 2021 Inauguration of the starting of the work is proposed to be conducted on 11.10.2021 at the WTP site ,Pongil by Hon.Minister Water Resources Dept. Thiruvananthapuram Project AE1
06 Oct 2021 Soil testing was conducted at WTP site at Pongil on 21-09-21 and Bhoomi pooja conducted at site. Thiruvananthapuram Project AE1
30 Sep 2021 Soil testing was conducted at WTP site at Pongil on 21-09-21 and Bhoomi pooja conducted at site. Thiruvananthapuram Project AE1
27 Sep 2021 Soil testing was conducted at WTP site at Pongil on 21-09-21 Thiruvananthapuram Project AE1