Overall Project Status

Status Date Overall Project Status Project Officer Contact
30 Sep 2022 Interconnection work is going on Mattannur WS Sn
24 Sep 2022 400 mm DI pipe laying work is going on Mattannur WS Sn
19 Sep 2022 400 mm DI pipe laying work is going on Mattannur WS Sn
12 Sep 2022 400 mm DI pipe laying work is going on Mattannur WS Sn
04 Sep 2022 400 mm DI pipe laying work is going on Mattannur WS Sn
01 Sep 2022 400 mm DI pipe laying work is going on Mattannur WS Sn
26 Aug 2022 (71% work completed) Thalipparamba to Kannur Airport road (Vaduvankulam-Chalode) is proposed for widening by KRFB, land acquisition is not completed, hence pipe laying work delayed. 500 mm di DI laying completed on 19th mile- Veliyambra road. Mattannur WS Sn
22 Aug 2022 (71% work completed) Thalipparamba to Kannur Airport road (Vaduvankulam-Chalode) is proposed for widening by KRFB, land acquisition is not completed, hence pipe laying work delayed. 500 mm di DI laying completed on 19th mile- Veliyambra road. Mattannur WS Sn
14 Aug 2022 (71% work completed) Thalipparamba to Kannur Airport road (Vaduvankulam-Chalode) is proposed for widening by KRFB, land acquisition is not completed, hence pipe laying work delayed. 500 mm di DI laying completed on 19th mile- Veliyambra road. Mattannur WS Sn
05 Aug 2022 (71% work completed) Thalipparamba to Kannur Airport road (Vaduvankulam-Chalode) is proposed for widening by KRFB, land acquisition is not completed, hence pipe laying work delayed. 500 mm di DI laying completed on 19th mile- Veliyambra road. Mattannur WS Sn