Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
13 Mar 2023 | 110 mm pipe laying remaining due to undecided KRFB road alignment | Mattannur WS Sn | |
02 Mar 2023 | 110 mm pipe laying remaining due to undecided KRFB road alignment | Mattannur WS Sn | |
25 Feb 2023 | 110 mm pipe laying remaining due to undecided KRFB road alignment | Mattannur WS Sn | |
20 Feb 2023 | 110 mm pipe laying remaining due to undecided KRFB road alignment | Mattannur WS Sn | |
09 Feb 2023 | 110 mm pipe laying remaining due to undecided KRFB road alignment | Mattannur WS Sn | |
02 Feb 2023 | 110 mm pipe laying remaining due to undecided KRFB road alignment | Mattannur WS Sn | |
28 Jan 2023 | 110 mm pipe laying remaining due to undecided KRFB road alignment | Mattannur WS Sn | |
23 Jan 2023 | 110 mm pipe laying remaining due to undecided KRFB road alignment | Mattannur WS Sn | |
19 Jan 2023 | 110 mm pipe laying remaining due to undecided KRFB road alignment | Mattannur WS Sn | |
16 Jan 2023 | 110 mm pipe laying remaining due to undecided KRFB road alignment | Mattannur WS Sn |