- KIIFB-Project-11-Replacing 350 mm dia AC...
KIIFB-Project-11-Replacing 350 mm dia AC pipe of distribution main of zone II-Kolecheery WSS with DI pipes from Vaduvankulam to Panayathamparamba Break pressure tank for enhancement of coverage in Kuttiattoor, Koodali, Munderi and Keezhallur panchayaths
Project |
KIIFB-Project-11-Replacing 350 mm dia AC pipe of distribution main of zone II-Kolecheery WSS with DI pipes from Vaduvankulam to Panayathamparamba Break pressure tank for enhancement of coverage in Kuttiattoor, Koodali, Munderi and Keezhallur panchayaths |
Project Code |
KNRKIIFB01192315 |
Type |
Main project |
Funding Agency |
KIIFB |
Category |
KIIFB |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
Project-11-Replacing 350 mm dia AC pipe of distribution main of zone II-Kolecheery WSS with DI pipes from Vaduvankulam to Panayathamparamba Break pressure tank for enhancement of coverage in Kuttiattoor, Koodali, Munderi and Keezhallur panchayaths |
Status |
Completed |
District |
Kannur |
Executing Office |
Kannur WS Dn |
AS Amount (Rs) |
74100000
|
AS Number |
WRD005-131-PA-01 |
TS Amount (Rs) |
74100000 |
TS Number |
2020-2021/2019/7005 |
Total Bill Submitted (Rs) |
26917282 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
40000 |
Capacity in MLD |
0.00 |
Actual Project Completion Date |
30 Sep 2022 |
Coverage |
Population benefitted-40000 |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
KIIFB-Project-11-Replacing 350 mm dia AC pipe of distribution main of zone II-Kolecheery WSS with DI pipes from Vaduvankulam to Panayathamparamba Break pressure tank for enhancement of coverage in Kuttiattoor, Koodali, Munderi and Keezhallur panchayaths |
Mattannur PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
10 Jul 2023 |
work completed |
Mattannur WS Sn |
|
30 Jun 2023 |
Reconnection work is going on |
Mattannur WS Sn |
|
26 Jun 2023 |
Inter connection work is going on. |
Mattannur WS Sn |
|
19 Jun 2023 |
Inter connection work is going on. |
Mattannur WS Sn |
|
12 Jun 2023 |
Inter connection work is going on. |
Mattannur WS Sn |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
18/01/2019 |
Scheduled date of Completion of the Project |
30 Sep 2022 |
Expected date of Completion |
30/06/2023 |
Processing Dates
AS Date |
18 Jan 2019 |
TS Date |
24 Feb 2021 |