Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
12 Nov 2022 | 110 mm pipe laying remaining due to undecided KRFB road alignment | Mattannur WS Sn | |
07 Nov 2022 | 110 mm pipe laying remaining due to undecided KRFB road alignment | Mattannur WS Sn | |
03 Nov 2022 | 110 mm pipe laying remaining due to undecided KRFB road alignment | Mattannur WS Sn | |
28 Oct 2022 | 110 mm pipe laying remaining due to undecided KRFB road alignment | Mattannur WS Sn | |
24 Oct 2022 | DI pipe laying completed | Mattannur WS Sn | |
21 Oct 2022 | DI pipe laying completed | Mattannur WS Sn | |
17 Oct 2022 | DI pipe laying completed | Mattannur WS Sn | |
13 Oct 2022 | Interconnection work completed | Mattannur WS Sn | |
10 Oct 2022 | Interconnection work completed | Mattannur WS Sn | |
06 Oct 2022 | Interconnection work completed | Mattannur WS Sn |