10 Dec 2021 160 mm PVC pipe 708. m Laid , 110 mm PVC pipe 420 m laid , 250 mm DI K9 pipe-18 m laid & 90 mm PVC rider pipe line 18 m laid. Mattannur WS Sn
02 Dec 2021 160 mm PVC pipe 708. m Laid & 110 mm PVC pipe 252 m laid. Mattannur WS Sn
22 Nov 2021 Wok started on 19.11.2021 and 160 mm PVC pipe 102. m Laid Mattannur WS Sn
15 Nov 2021 Work order issued Mattannur WS Sn
02 Nov 2021 tender evaluation stage Mattannur WS Sn
30 Oct 2021 tender evaluation stage Mattannur WS Sn
28 Oct 2021 tender evaluation stage Mattannur WS Sn
24 Oct 2021 tender evaluation stage Mattannur WS Sn
20 Oct 2021 tender evaluation stage Mattannur WS Sn
16 Oct 2021 tender evaluation stage Mattannur WS Sn