07 May 2022 |
400 mm DI K9 pipe 2300m Laid, 250 mm DI K9 pipe-1200 m laid , 160 mm PVC pipe 708. m Laid , 110 mm PVC pipe 2600 m laid , 90 mm PVC rider pipe line 3100 m laid.500 mm DI pipe 250 m laid & 500 mm MS fabrication work completed at Kala road bridge |
Mattannur WS Sn |
|
19 Apr 2022 |
400 mm DI K9 pipe 2200m Laid, 250 mm DI K9 pipe-1200 m laid , 160 mm PVC pipe 708. m Laid , 110 mm PVC pipe 700 m laid , 90 mm PVC rider pipe line 3100 m laid.500 mm DI pipe 110 m laid & 500 mm MS fabrication work completed at Kala road bridge |
Mattannur WS Sn |
|
11 Apr 2022 |
400 mm DI K9 pipe 1600m Laid, 90 mm PVC rider line 1600 m laid,160 mm PVC pipe 708. m Laid , 110 mm PVC pipe 420 m laid , 250 mm DI K9 pipe-930 m laid & 90 mm PVC rider pipe line 930 m laid.500 mm DI pipe 110 m laid & 500 mm MS fabrication work completed at Kala road bridge |
Mattannur WS Sn |
|
16 Mar 2022 |
400 mm DI K9 pipe 1600m Laid, 90 mm PVC rider line 1600 m laid,160 mm PVC pipe 708. m Laid , 110 mm PVC pipe 420 m laid , 250 mm DI K9 pipe-800 m laid & 90 mm PVC rider pipe line 650 m laid.500 mm DI pipe 110 m laid & 500 mm MS fabrication work completed at Kala road bridge |
Mattannur WS Sn |
|
07 Mar 2022 |
400 mm DI K9 pipe 950 m Laid, 90 mm PVC rider line 950 m laid,160 mm PVC pipe 708. m Laid , 110 mm PVC pipe 420 m laid , 250 mm DI K9 pipe-800 m laid & 90 mm PVC rider pipe line 650 m laid.500 mm DI pipe 110 m laid & 500 mm MS fabrication work completed at Kala road bridge |
Mattannur WS Sn |
|
21 Feb 2022 |
400 mm DI K9 pipe 800 m Laid, 90 mm PVC rider line 800 m laid,160 mm PVC pipe 708. m Laid , 110 mm PVC pipe 420 m laid , 250 mm DI K9 pipe-650 m laid & 90 mm PVC rider pipe line 650 m laid.500 mm DI pipe 110 m laid & 500 mm MS fabrication work completed at Kala road bridge |
Mattannur WS Sn |
|
16 Feb 2022 |
400 mm DI K9 pipe 580 m Laid, 90 mm PVC rider line 580 m laid,160 mm PVC pipe 708. m Laid , 110 mm PVC pipe 420 m laid , 250 mm DI K9 pipe-500 m laid & 90 mm PVC rider pipe line 500m laid.500 mm DI pipe 110 m laid & 500 mm MS fabrication work completed at Kala road bridge |
Mattannur WS Sn |
|
09 Feb 2022 |
400 mm DI K9 pipe 470 m Laid, 90 mm PVC rider line 470 m laid,160 mm PVC pipe 708. m Laid , 110 mm PVC pipe 420 m laid , 250 mm DI K9 pipe-145 m laid & 90 mm PVC rider pipe line 145m laid.500 mm DI pipe 110 m laid & 500 mm MS fabrication work completed at Kala road bridge |
Mattannur WS Sn |
|
08 Feb 2022 |
400 mm DI K9 pipe 450 m Laid, 90 mm PVC rider line 450 m laid,160 mm PVC pipe 708. m Laid , 110 mm PVC pipe 420 m laid , 250 mm DI K9 pipe-145 m laid & 90 mm PVC rider pipe line 145m laid.500 mm DI pipe 110 m laid & 500 mm MS fabrication work completed at Kala road bridge |
Mattannur WS Sn |
|
03 Feb 2022 |
400 mm DI K9 pipe 260 m Laid, 90 mm PVC rider line 260 m laid,160 mm PVC pipe 708. m Laid , 110 mm PVC pipe 420 m laid , 250 mm DI K9 pipe-145 m laid & 90 mm PVC rider pipe line 145m laid.500 mm DI pipe 110 m laid & 500 mm MS fabrication work completed at Kala road bridge |
Mattannur WS Sn |
|