Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
16 Nov 2022 | 630FHTCs completed out of 2300, 7th and Part bill submitted | Vadanappilly AE | |
16 Nov 2022 | 630FHTCs completed out of 2300, 7th and Part bill submitted | Vadanappilly AE | |
14 Nov 2022 | 630FHTCs completed out of 2300, 7th and Part bill submitted. Panchayath roads applied in ROW for cutting permission. | Vadanappilly AE | |
10 Nov 2022 | 630FHTCs completed out of 2300, 7th and Part bill submitted. Panchayath roads applied in ROW for cutting permission. | Vadanappilly AE | |
07 Nov 2022 | 630FHTCs completed out of 2300, 7th and Part bill submitted. Panchayath roads applied in ROW for cutting permission. | Vadanappilly AE | |
03 Nov 2022 | 607FHTCs completed out of 2300, 7th and Part bill submitted. Panchayath roads applied in ROW for cutting permission. | Vadanappilly AE | |
31 Oct 2022 | 607FHTCs completed out of 2300, 7th and Part bill submitted. Panchayath roads applied in ROW for cutting permission. | Vadanappilly AE | |
27 Oct 2022 | 607FHTCs completed out of 2300, 7th and Part bill submitted. Panchayath roads applied in ROW for cutting permission. | Vadanappilly AE | |
25 Oct 2022 | 607FHTCs completed out of 2300, 7th and Part bill submitted. Panchayath roads applied in ROW for cutting permission. | Vadanappilly AE | |
25 Oct 2022 | 577 FHTCs completed out of 2300,7th and Part bill submitted. Panchayath roads applied in ROW for cutting permission. | Vadanappilly AE |