Overall Project Status

Status Date Overall Project Status Project Officer Contact
10 May 2022 561 FHTCs completed out of 2300,5th and Part bill submitted Vadanappilly AE
05 May 2022 573 FHTCs completed out of 2300,5th and Part bill submitted Vadanappilly AE
04 May 2022 573 FHTCs completed out of 2300,5th and Part bill submitted Vadanappilly AE
28 Apr 2022 495 FHTCs completed out of 2300,5th and Part bill submitted Vadanappilly AE
28 Apr 2022 495 FHTCs completed out of 2300,4th and Part bill submitted Vadanappilly AE
25 Apr 2022 495 FHTCs completed out of 2300,4th and Part bill submitted Vadanappilly AE
21 Apr 2022 495 FHTCs completed out of 2300,4th and Part bill submitted Vadanappilly AE
18 Apr 2022 485 FHTCs completed out of 2300,4th and Part bill submitted Vadanappilly AE
11 Apr 2022 479 FHTCs completed out of 2300,4th and Part bill submitted Vadanappilly AE
11 Apr 2022 463 FHTCs completed out of 2300,4th and Part bill submitted Vadanappilly AE