Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
10 May 2022 | 561 FHTCs completed out of 2300,5th and Part bill submitted | Vadanappilly AE | |
05 May 2022 | 573 FHTCs completed out of 2300,5th and Part bill submitted | Vadanappilly AE | |
04 May 2022 | 573 FHTCs completed out of 2300,5th and Part bill submitted | Vadanappilly AE | |
28 Apr 2022 | 495 FHTCs completed out of 2300,5th and Part bill submitted | Vadanappilly AE | |
28 Apr 2022 | 495 FHTCs completed out of 2300,4th and Part bill submitted | Vadanappilly AE | |
25 Apr 2022 | 495 FHTCs completed out of 2300,4th and Part bill submitted | Vadanappilly AE | |
21 Apr 2022 | 495 FHTCs completed out of 2300,4th and Part bill submitted | Vadanappilly AE | |
18 Apr 2022 | 485 FHTCs completed out of 2300,4th and Part bill submitted | Vadanappilly AE | |
11 Apr 2022 | 479 FHTCs completed out of 2300,4th and Part bill submitted | Vadanappilly AE | |